Grange confident of meeting FY output target

10th September 2015

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Pellet producer Grange Resources is optimistic about its targeted production for the full 2015, despite a 65-day downtime at one of its two mills.

The company said on Thursday that owing to the highly successful refurbishment of the mill, which delivered increased production rates and greater efficiency, Grange was on track to produce some 2.5-million tonnes of magnetite concentrate for the full-year, which was on par with that produced in 2014.

Concentrate production from the Savage mine would be pumped to the pellet plant at Port Latta, in Tasmania, to produce some 2.6-million tonnes of pellets.

Meanwhile, Grange would proceed with the refurbishment of its second mill during the June 2016 quarter, with the shutdown expected to take some 55 days.

The completion of the two mill upgrades would underpin an increase in total production capacity to 2.7-million tonnes a year and would significantly reduce operating risks, the company said.

However, depending on the results of the mine rescheduling work, Grange could elect to optimise mining rates to the level needed to sustain pellet production around current rates. This would mean keeping concentrate production at around 2.6-million tonnes a year.

The optimisation strategy, which was expected to be completed later this year, was part of Grange’s overarching strategy to continue reducing costs, maximising margins and growing free cash flow rather than simply increasing production.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

MBE Minerals SA (Pty) Ltd
MBE Minerals SA (Pty) Ltd

Your global lifecycle technology & service partner for materials & minerals processing equipment for coal, iron ore, copper, manganese & other...

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.056 1.095s - 110pq - 2rq
Subscribe Now