Galan investigating bigger project in Argentina
PERTH (miningweekly.com) – Lithium developer Galan Lithium is looking at options to expand the production at its proposed Hombre Muerto West project, in Argentina, as well as to decrease capital expenditure and operating costs.
A preliminary economic assessment of the project in late 2020 found that the project could support the production of 20 000 t/y of battery grade lithium carbonate equivalent over a mine life of 40 years.
The study estimated that the project would require an initial capital investment of $439-million, which included a 30% contingency, with cash costs of production estimated at $3 518/t of lithium carbonate.
However, Galan MD Juan Pablo Vargas de la Vega told the Paydirt Battery Minerals conference, in Perth, that the company is investigating the potential to increase the production rate at Hombre Muerto West.
Furthermore, the preliminary economic assessment was performed at a time when the Del Condor concession did not form part of the tenement holdings, however, with the concession now granted, Galan has the potential to extend and add ponds to the north of the project area, meaning a potential reduction in capital costs.
The company is also looking at reducing operating cost, Vargas said, through the reduction in the consumption of reagents and an increase in recoveries.
Furthermore, Vargas said that the company earlier this year also announced that its high-grade lithium chloride concentrate had increased by 25% compared with the preliminary economic assessment study, giving the company the flexibility to place its lithium for downstream products anywhere in the world without the burden of high logistics costs, a high carbon footprint, or waste management.
“Galan is evaluating the commercial potential in the global market for its high grade lithium chloride concentrate as feed for lithium battery products,” he said.
“We have a way to get to the market quick, to become a producer, and we won’t have to be dependent on anyone to do so.”
Galan is hoping to start feasibility studies into the Hombre Muerto West project by the second quarter of next year, along with a pilot plant.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation