Frontier copper project, Democratic Republic of Congo
Name of the project and location
Frontier copper project, Democratic Republic of Congo.
Project description
The project will involve the greenfield development of all mine infrastructure, including power supply, water supply, offices, workshops and other buildings, mobile equipment and fuel storage, to enable the openpit mining and processing of primary sulphide ore.
Power for the project will be supplied from an existing substation approximately 28 km to the west in Zambia. Water will be supplied from mine dewatering.
The site has the advantage of being relatively close to significant existing mine developments in the Zambian Copperbelt.
The current measured and indicated sulphide resource at a 0,35% copper cut-off totals 182,1-million tons grading 1,16% total copper, which contains 2,1-million tons of copper. In addition to the sulphide resource, the project hosts a measured and indicated oxide/mixed resource at a 0,35% copper cut-off of 26-million tons grading 1,19% total copper, which contains 0,31-million tons of copper.
During the life-of-mine, Frontier is expected to produce 1,43-million tons of copper in concentrate.
Value
The total construction capital cost for the Frontier project is expected to be $226,4-million. Life-of-mine capital for the project is estimated at $448,7-million.
Duration
Commissioning and commercial production are expected in the third quarter 2007.
Breakdown of main contracts
Not stated.
Client
First Quantum Minerals.
Latest developments
None stated.
Participants
None stated.
On budget and on time?
Not stated.
Contact details for project information
First Quantum Minerals, tel +1 604 688 6577, fax +1 604 688 3818 or email info@fqml.com .
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation