Fortescue posts record quarterly output
PERTH (miningweekly.com) – Iron-ore major Fortescue Metals has reported another record quarterly production, with the June shipping rates exceeding expectations by some five-million tonnes.
The Australian miner told shareholders on Tuesday that output for the June quarter reached 25-million tonnes, a 24% increase on the previous quarter and a 40% increase on the previous comparable quarter.
Ore mined increased to 34.3-million tonnes, up 35% on the previous quarter, as strip ratios declined and operations continued to focus on efficiencies.
Fortescue said that the record results were achieved despite unseasonable wet weather conditions, which impacted on production performance at the port and mine sites.
The record production was achieved on the back of Fortescue’s continued expansion work, and the miner noted that loading capacity at the port also increased during the quarter to 120-million tons a year from two berths and three shiploaders, and would further increase to 155-million tonnes a year when the fourth berth and third shiploader was commissioned during July, in advance of the Kings mine completion.
The Kings development, at the Solomon Hub, was also progressing in line with expectations, Fortescue said, adding that commissioning is scheduled for the December quarter.
The Kings mine would allow Fortescue to produce at a run rate of 155-million tonnes a year across its supply chain by the end of the 2014 wet season.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation