Flsmidth Completes Early Engineering For Ivanplats Platreef Project Winders
This article has been supplied.
Company Announcement - FLSmidth recently completed the early engineering contract for the production, service and auxiliary winders for Ivanplats Platreef Project No2 Shaft. The early engineering of the three separate winders was necessary to facilitate the design of the headframe structure by Murray & Roberts Cementation. Mark Sheward, sales manager mine shaft systems for FLSmidth, says that the contract award was based on the company’s 60-plus years’ of experience and an extensive reference base of installations. The largest Koepe winders previously supplied by FLSmidth are the two 6.5 metre diameter units at Impala 16 shaft and their successful implementation forms the basis of the design and engineering undertaken for the Ivanplats Platreef Project winders.
“Experience is critical in projects of this nature and the ability to adapt to changing conditions is one which differentiates FLSmidth. Each of the two 6 metre diameter Koepe winder installations with drums, brake systems and drives needs to be accommodated within the constraints of the headframe dimensions. The solution we provided involved installing the two Koepe winders at 90° degree angles to each other, with the auxiliary winder being installed in a lower level,” Sheward explains.
During the early engineering phase, FLSmidth made use of Finite Element Analysis (FEA) to establish and verify the stress loading in the final design. Other supplied data included dimensions, loads, required tolerances, stiffness requirements and the position and length of the anchor bolts, as well as the mass and dimensions of the major components to be lifted into the headframe.
Both the production and service winders are four rope friction winders. The production winder will hoist two 40 ton skips while the service winder will be equipped with a man/material cage and counterweight. The rock or production winder is being designed for a rope speed of 18 metres per second while the man/material winder will operate at 10 metres per second. The auxiliary winder, with a rope speed of 6 metres per second, will be a 2.4 metre diameter, 1.2 metre wide single drum unit and could initially be ground-mounted and used for shaft equipping before being relocated to the head frame on completion of shaft sinking.
The shaft depth is approximately 1 050 metres and braking will be effected on all three winders by a 4-channel closed loop hydraulic system incorporating disc brakes.
New small winder design
The auxiliary winder forms part of the new small winder design which FLSmidth has been developing over the past year. This ongoing development work allows design optimisation and a reduction in the weight of the actual winder, as well as the simplification of the clutch design.
During the design stages, extensive use was made of software programmes, including FEA. “Best practice benchmarking was used and this allowed for the formulation of a parametric model which can be either up- or downscaled to accommodate specific application requirements. This has dramatically reduced the engineering time required and ultimately translates into the facilitation of faster responsiveness to customer requests for design/engineering on small single drum and double drum winders (with clutch) of up to 3.66 metres in diameter,” says Sheward.
He points out that FLSmidth’s South African office is the global technology centre for all winders within the entire international organisation and Africa has the largest installation base of winders. This provides customers on the African continent with a distinct advantage, as all engineering for winders is undertaken in the Johannesburg offices. This close proximity to customers aids information flow and facilitates faster responsiveness.
In addition to the early engineering for the winders, FLSmidth also secured the contract for the design and engineering of the conveyances for these winders. This contract comprises the detailed design of the two 40 ton skips for the production winder and a 40 ton double deck cage and cage counterweight for the man/material hoist. The skips will incorporate hydraulic dump mechanisms. All work for the skips and cages will be undertaken at the FLSmidth technology centre for conveyances in Orilia, Canada, where engineers have access to the latest technical information.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation

















