First production at Lesotho diamond mine to be delayed – Firestone
JOHANNESBURG (miningweekly.com) – Adverse weather conditions and increased overburden at the Liqhobong mine development project, in Lesotho, have led to a R156-million increase in costs, Aim-listed developer Firestone Diamonds said on Tuesday.
The diamond company further revealed that production would now only start in the fourth quarter, rather than in the first half of 2016 as previously anticipated.
"Despite adverse weather, increased overburden and the larger rocks encountered at site, the project continues to make good progress,” CEO Stuart Brown commented.
He noted that the costs of additional work crews and the acceleration of certain key areas adopted to meet the revised schedule through to production were “all catered for” within the project's original $185.4-million budget.
“We will continue to work to find other ways to accelerate work streams and improve on the revised completion schedule and will keep shareholders updated as we achieve these milestones," he added.
Despite the increased earthworks, the company was confident that it could make up lost time through remedial action. It had been working on rescheduling additional earthworks.
“A number of initiatives have been implemented to reduce any resulting delay to the overall programme, including the introduction of an additional shift, additional work crews and redeployment of contractors to areas that are on the critical path from areas which are ahead of schedule,” Firestone said in a statement.
Further, the company sought to delay the delivery of constructed steel and delay other work streams to allow the earthworks to catch up, while, at the same time, reducing the cash drawdown requirements and associated financing charges.
By end-May, Firestone had spent R830-million on the project.
Meanwhile, Firestone signed an agreement with Storm Mountain Diamonds, the owner of the Kao mine, in Lesotho, to use the power line alongside Firestone and to contribute R94.5-million of the revised project costs to connect the mines to the national electricity grid.
The grid power project was progressing ahead of schedule and was within budget, with connection to the grid expected in the third quarter. The company estimated that it had made net savings of R70.5-million.
“This is an important milestone for the company, as it will allow Liqhobong to use grid power on site during construction earlier than planned, thus reducing the diesel generating costs and realising a small saving,” it noted.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation















