First gold pour at Andy Well in August
PERTH (miningweekly.com) – Junior gold miner Doray Minerals has started commissioning of the Andy Well gold processing plant, in Western Australia.
The ASX-listed Doray said that commissioning was expected to take some four weeks, meaning that gold production at Andy Well would likely start in August.
MD Allan Kelly said on Friday that the original development schedule outlined in the bankable feasibility study, had construction and development starting in September 2012, with first gold production initially expected in July.
“Due to permitting delays, we didn’t actually start work on site until mid-November last year. Using the same timeline, first gold production wasn’t, therefore, expected until September of this year. Instead, despite starting over two months late, and pending a successful completion of commissioning, we should be pouring first gold within a few weeks of that original schedule,” he said.
Meanwhile, Doray noted that underground development of the high-grade Wilber lode deposit continued on schedule, with first ore expected during July. The first stoping ore was scheduled for September/October, once sufficient capital development had been completed.
As with the Stage 1 openpit operations, ore from the underground mine would be stockpiled for future treatment once the processing plant was commissioned.
The Andy Well project currently hosted a resource of some 1.22-million tons, at 11.3 g/t gold for 444 000 contained ounces.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation