Firestone Diamonds’ Liqhobong mine on track for year-end production

1st April 2016

By: Anine Kilian

Contributing Editor Online

  

Font size: - +

Aim-listed international mining and exploration company Firestone Diamonds’ Lesotho-based Liqhobong mine was 68% complete at the end of February and remains on track for initial production in the fourth quarter.

Firestone reported last week that all critical civils and earthworks were complete and its focus was now on the erection of the main plant.

The company had updated Liqhobong’s diamond resource and reserve based on a new geological model, increasing bottom cutoff (BCO) and excluding boart carats. The new mine plan confirmed enhanced project economics.

Further, the revised capital budget of R2.1-billion for the project remained within the original $185.4-million budget, owing to the depreciation of the South African rand against the US dollar.

The company added that R1.3-billion, or 63%, had been spent on the project against the revised capital budget.

Meanwhile, a total of R1.67-billion in orders out of the revised total of R1.77- billion in engineering, procurement, construction and management (EPCM) contracts had been placed at the end of December 2015, representing 94% of the total EPCM budget. This was done to remove cost escalation risk.

“The six months to December 31, 2015, saw substantial development at Liqhobong and, importantly, we have continued this into 2016. The project remains within budget and on target to achieve first production during the fourth quarter of this year,” said Firestone CEO Stuart Brown.

The project had a staff complement of 952 employees and contractors, of which 82% were Lesotho citizens. The mine’s grid power project was completed within budget and ahead of schedule in October last year and Liqhobong was now connected to grid power, which allowed for “a consistent supply of electricity on site for the remainder of construction and through to production”.

“In October 2015, we were pleased to announce the completion of a new mine plan and project economics – the culmination of over a year’s work – which further derisked the project and enhanced its economics,” added Brown.

He noted that all significant civils and earthworks that were on the critical path had been completed and that the site had been handed over to the structural, mechanical, plate and pipework (SMPP) contractors for the erection of the main plant.

As part of the project team’s plans to accelerate construction and recover time lost at the beginning of the project, fabrication of the SMPP started ahead of the original planned timeline to ensure that erection did not experience delays resulting from the manufacturing process.

“As a result, both the erection and fabrication processes are ahead of schedule, with fabrication progress at 98.7% versus the 96.2% revised baseline, while erection progress is at 22.6% versus the 21.3% revised baseline as at the end of February 2016,” he noted.

During the period, the project team began preparing for operational readiness ahead of the expected fourth-quarter production.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
MBE Minerals SA (Pty) Ltd
MBE Minerals SA (Pty) Ltd

Your global lifecycle technology & service partner for materials & minerals processing equipment for coal, iron ore, copper, manganese & other...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.042 0.981s - 110pq - 2rq
Subscribe Now