Name of the Project
Finniss lithium project.

Location
The project is located near Darwin, in the Northern Territory, Australia.

Project Owner/s
ASX-listed Core Lithium.

Project Description
A definitive feasibility study (DFS) has confirmed that Core is well positioned to be the next lithium producer in Australia.

The April 2019 DFS focused on the development of ore reserves within the first two orebodies – Grants and BP33 – over an initial 3.5-year period.

Project comprises a low-risk, openpit mining operation and dense-media separation processing up to 180 000 t/y of high-quality lithium concentrate with robust margins.

The project will have a design throughput of one-million tonnes a year and scheduled production of 481 018 t.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 10% discount rate, of A$114-million and an internal rate of return of 80%.

Capital Expenditure
Startup capital expenditure is estimated at A$73-million.

Planned Start/End Date
An updated definitive feasibility study for the Finniss project is due in the first half of 2021, ahead of a final investment decision.

Latest Developments
Battery-grade lithium hydroxide has been produced from a spodumene mineral concentrate sample from the Finniss project.

The scoping-level testwork has demonstrated that the conventional direct flowsheet be applied to the processing of the mineral concentrates from Finniss to produce battery-grade lithium hydroxide monohydrate.

The company is now considering the downstream value potential for the project, given its synergies with the adjacent Middle-Arm industrial infrastructure near Darwin, as well as the alignment with Australia’s Modern Manufacturing Strategy and the rapid expansion of global battery lithium supply chains to meet increasing demand.

A final investment decision on the Finniss project is due in the third quarter of 2021, and Core is completing concentrate DFSs and finalising offtake negotiations.

Key Contracts, Suppliers and Consultants
Primero, Qube and Lucas TCS (key contractors).

Contact Details for Project Information
Core Lithium, tel +61 8 8317 1700 or email info@corelithium.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Virtual Gas Network (Pty) Ltd
Virtual Gas Network (Pty) Ltd

Virtual Gas Network supplies compressed natural gas via a virtual gas distribution network.

VISIT SHOWROOM 
MBE Minerals SA (Pty) Ltd
MBE Minerals SA (Pty) Ltd

Your global lifecycle technology & service partner for materials & minerals processing equipment for coal, iron ore, copper, manganese & other...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.049 0.878s - 111pq - 2rq
Subscribe Now