Few municipalities in a position to implement embedded generation initiatives
Even though government paved the way for municipalities to generate or procure their own electricity from independent power producers (IPPs) a little under two years ago, only 25% of them are equipped with either a basic or comprehensive small-scale embedded generation (SSEG) process or are in a position to put one in place.
A further 25% of municipalities do not have the internal capacity to establish or manage these processes, but may be able to do so with some support, while the remaining 50% are not in a state to handle any additional responsibility, owing to long-standing financial difficulty or mismanagement issues, Sustainable Energy Africa director Mark Borchers noted last month.
He shared his insights on how large-scale embedded generation was being rolled out across local government during a webinar hosted by the Association of Municipal Electricity Utilities and the South African Institute of Electrical Engineers on August 23.
He explained that while SSEG had been happening at municipalities for quite some time, and many had managed this reasonably well, bringing large energy users into the network was a “whole new movement” that needed an understanding of the legalities and required proper processes to be in place.
Among the local government authorities that have successfully pulled off SSEG and larger-scale embedded generation is the City of Ekurhuleni, in Gauteng.
The city’s chief engineer, Hendrik Raedeni, said the metro had an embedded generation integration framework in place, as well as an IPP programme. Ekurhuleni comprises nine towns, each with an independent distribution grid.
Through the city’s IPP programme, which was launched in 2017, a total of 47 IPPs have been appointed through a request for proposals process to supply electricity in the metro.
The city has signed 90% of the required power purchase agreements (PPA) with these IPPs, with three IPPs undertaking grid integration studies at the moment and ten having letters of intent to fund from investors in place.
The estimated start of construction for some of the IPPs is December this year and January next year, while the first generation units from these projects will be on line in 12 months’ time.
The city only accepted embedded IPPs with capacities of 5 MW and above, with no wheeling involved.
Ekurhuleni does have a wheeling framework in place nonetheless, and believes it can present a new revenue stream opportunity for itself and other local government authorities.
The 47 IPPs have a combined proposed capacity of 683 MW, of which 298 MW will comprise solar, 139 MW waste-to-energy and 195 MW gas.
Raedeni said Ekurhuleni hoped to save just under R14-billion through this programme, which would have otherwise been paid to Eskom over 20 years. The programme helped to ensure more affordable energy for customers, avoided power losses as no long transmission lines were involved, created jobs and mitigated against climate change.
To pull off a successful energy procurement programme, Raedeni suggested municipalities start with small but fundable projects, and ensure good credit ratings, since they aid PPA fundability, as does a good payment record to Eskom.
“Investors want risk to be shared and need to be assured government will pay its dues,” he stressed.
Council for Scientific and Industrial Research (CSIR) principal researcher Warrick Pierce, meanwhile, emphasised that the electricity market was evolving and that municipalities’ business models and planning processes should do the same.
He highlighted that they could no longer remain dependent on one source of supply, nor remain a traditional bulk reseller of electricity.
The CSIR has witnessed an evolution to more decentralised energy operations, with more regional and local municipal energy master plans arising.
Pierce said Municipal Energy Master Plans (MEMPs) proved useful in balancing supply and demand, and were considered least-cost options, if done well and based on long-term planning.
The CSIR has, in collaboration with the Department of Mineral Resources and Energy, the South African-German Energy Partnership and the South African Local Government Association, been engaging metropolitan municipalities on understanding the impacts of SSEG on networks.
Municipalities were evaluated for their readiness to facilitate SSEG interconnection through a gap analysis, on which the CSIR based the development of support tools to assist municipalities with detailed assessments of integrating SSEG into their networks.
In particular, the CSIR partnered with three municipalities to assess the technical grid impacts of SSEG on their networks to determine the support required and inform on areas of concern .
Pierce said the load flow assessment tool that the CSIR developed helped municipalities calculate a steady-state solution of an electric power network, which could prove useful for power system planning and operation.
He added that load flow could be used to gain insight into a network’s performance over a range of operating conditions.
Commenting on how municipalities should go about crafting an MEMP, he said they should consider the status quo, including customer demand, technology costs, technical performance, local resource assessment, electrical network constraints, and Eskom and municipal tariffs; forecasts and analyses, including demand forecasts, projected tariffs, rooftop photovoltaic analyses and assumed wheeling charges; capacity expansion modelling at utility scale, which should include scenarios on regional expansion and the associated costs, as well as when to retire assets; and impact assessments, including considerations on greenhouse-gas emissions reductions, job creation and economic contribution.
University of the Witwatersrand electrical engineering professor Chandima Gomes suggested that municipalities take full advantage of the 2020 amendments to the Electricity Regulation Act and think beyond procurement to self-generation, exploring all possibilities to generate energy within municipal jurisdictions, lest they become redundant if micro-grids continued to pop up and they lost sources of revenue.
He advised municipalities to obtain external input from experts when considering technology types, sizing, placement, operation and maintenance of a new power source and network.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation















