Name of the Project
Falchani lithium project.

Location
The project is located on the Macusani plateau, in the Puno district of south-eastern Peru.

Project Owner/s
Plateau Energy Metals.

Project Description
An independent preliminary economic assessment (PEA) has demonstrated the project’s ability to become a large, long-life producer of low-cost, high-quality low-impurity battery-grade lithium carbonate.

The Falchani project is highly amenable for development by conventional openpit truck-and-shovel methods.

The base case, which encompasses the entire mineral resource estimate for the Falchani and Ocacasa 4 concessions, envisages the production of 63 000 t/y of battery-grade lithium carbonate over 33 years, increasing to 85 000 t/y at a steady-state throughput of six-million tonnes a year.

The PEA includes the construction of a 1 700 t/d sulphur-burning acid plant on site to produce, on average, 1 500 t/d of sulphuric acid. In subsequent phases, additional modules are added to meet expanded processing capacity.

The PEA also represents an alternative case, which includes only the mineral resources from the Falchani concession.

Like the base case, the alternative case will use the same operating parameters, metal price and selling costs, and consists of an openpit mine, an associated processing facility and on- and off-site infrastructure. In this scenario, the project is projected to have a 26-year mine life, with Phase 1 having a milling rate of 1.5-million tonnes a year and Phase 2 three-million tonnes a
year.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
At a base case of $12 000/t lithium carbonate, the project has a pretax net present value, at an 8% discount rate, of $2.71-billion and an internal rate of return of 24.2%, with a payback of 4.3 years (undiscounted).

Capital Expenditure
Initial capital expenditure is estimated at $587-million.

Planned Start/End Date
The construction period has been scoped for 24 months.

Latest Developments
None stated.

Key Contracts and Suppliers
DRA, working with ANSTO Minerals, with input from M.Plan International (process flowsheet)

Contact Details for Project Information
Plateau Energy Metals, tel +1416628 9600 or email Info@PlateauEnergyMetals.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
ECG Engineering
ECG Engineering

ECG provides specialised electrical engineering services to the Mining, Utilities, Materials Handling and Industrial industries, with extensive and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.041 1.172s - 111pq - 2rq
Subscribe Now