Eyre Peninsula graphite project, Australia

11th November 2016

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name of the Project
Eyre Peninsula graphite project.

Location
The project is located near the township of Cleve, in South Australia.

Client
Archer Exploration.

Project Description
A scoping study completed on the project has shown that Eyre has robust economics and is a technically low-risk graphite development when considered against a strong graphite and graphene market outlook.

The project has mineral resources estimated at 2.8-million tonnes grading 6.5% total graphitic carbon. The study is based on the mining and production of graphite from only the Campoona shaft, Central Campoona and only 10% (by tonnes of contained graphite) of the total Wilclo South mineral resource.

Estimated average yearly production (after ramp-up) is estimated at 11 592 t of graphite concentrate increasing to 18 648 t after Year 7.

The project has a mine life of 17 years.

Mining will be openpit methods using conventional truck-and-excavator operations. Mining trucks will transport material from the pit to the run-of-mine pad and waste-rock storage facilities adjacent to the mine.

The study is based on the construction of Sugarloaf – a centralised graphite mineral processing plant. The plant will comprise crushing, blunging, rougher flotation, concentrate milling, cleaner/recleaner flotation and chemical leaching.

Jobs to be Created
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 10% discount rate, of A$126-million and an internal rate of return of 62%, with a payback of 1.8 years.

Value
The project has an estimated pre-production capital of A$36-million from years 1 to 3, with a further A$25-million in capital allocated for expansion – $18-million in Year 6 and $7-million in Year 14.

Duration
Not stated.

Latest Developments
The scoping study supports Archer’s decision to lodge a mining lease application in the fourth quarter of 2016, with the subsequent granting of a mining lease expected in mid-2017.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Archer Exploration, tel +61 8 8272 3288, fax +61 8 8272 3888 or email info@archerexploration.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 
Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.05 0.716s - 111pq - 2rq
Subscribe Now