https://www.miningweekly.com

ERA reports production results after recent Ranger restart

ERA reports production results after recent Ranger restart

Photo by Bloomberg

9th October 2014

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Uranium miner Energy Resources of Australia (ERA) produced 566 t of uranium oxide (U3O8) during the three months to September, following the progressive restart of its Ranger mine, in the Northern Territory.

Plant operations at the Ranger mine have been suspended since December last year, after a mixture of slurry moved outside the containment area, following the failure of a leach tank.

The miner undertook a progressive restart of the Ranger processing plant in June, after receiving approval from the state and federal governments. While about 46 000 t of ore was milled during the June quarter, no U3O8 was drummed or packed for shipment.

Despite the operation’s recent restart, the September quarter production levels were only 7% below those achieved in the previous corresponding period.

ERA told shareholders on Thursday that progress to full mill throughput was achieved during the quarter, and milling rates were higher in the September quarter than in the previous corresponding quarter.

However, the higher milling rates were offset by lower plant recovery, which resulted in the lower production of U3O8, compared with the 2013 September quarter. The plant recovery was affected by restrictions on the availability of leach tanks during the period under review.

ERA noted that progressive rehabilitation of the Ranger project area also continued during the quarter, adding that the initial backfill of Pit 3 was now completed.

The infrastructure required to enable the conversion of Pit 3 into a tailings repository was on schedule to be installed by the end of the year.

ERA recently submitted a draft environmental impact statement on its Ranger 3 Deeps underground mine to the Northern Territory Environmental Protection Authority and the commonwealth Department of the Environment.

The project would have a significantly smaller footprint than the previous opencut operation at Ranger, and first production has been targeted for late 2015, pending board and regulatory approval.

ERA noted that the prefeasibility study into the Ranger 3 Deeps underground mine was scheduled for completion by the end of the fourth quarter this year.

Edited by Mariaan Webb
Creamer Media Contract Publishing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

SafeQuip
SafeQuip

SafeQuip is a leading distributor and manufacturer of fire safety solutions, offering a comprehensive range of products designed to meet all...

VISIT SHOWROOM 
Rosond
Rosond

ROSOND provides fast, efficient, safe, and cost-effective drilling and grouting services to mining and exploration industries throughout Africa.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.051 0.723s - 111pq - 2rq
Subscribe Now