https://www.miningweekly.com

Epanko graphite project, Tanzania

29th September 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Epanko graphite project.

Location
Tanzania.

Client
Kibaran Resources.

Project Description
An updated bankable feasibility study (BFS) has demonstrated a highly robust business case for a 60 000 t/y operation at Epanko and has also substantially enhanced and derisked the project’s development.

The project has an ore reserve of 11.7-million tonnes grading 8.32% total graphitic carbon for 971 000 t graphite, supporting an 18-year mine life.

The BFS is based on a mining contractor scenario.

Mining will be undertaken using the conventional drill-and-blast technique, with the fleet comprising an 80 t backhoe excavator and 40 t off-highway haul trucks.

Mining operations will start in the Eastern pit and progress to the Western pit in Year 6 to the scheduled reserve exhaustion in Year 16. The average life-of-mine strip ratio is expected to be 0.4:1 (waste to ore).

The Western deposit entails mining a strike length of 1 360 m along the top of the ridge to a depth of 210 m in the south. 

The Eastern deposit, located partially over a hill within a small valley, will be mined to a depth of 125 m and will have a strike extent of 350 m.

The process plant is designed with a throughput capacity of 720 000 t/y for an average total graphitic carbon grade of 96% and average production of 60 000 t/y. The plant is based on a crush-and-grind comminution circuit (two-stage crushing circuit with single-stage rod mill), followed by rougher flotation.

The tailings are reground in a ball mill before entering the scavenger flotation. The rougher and scavenger concentrates will be combined and transferred into the primary cleaner section, comprising polishing mills and cleaner flotation banks.

The concentrate will then be screened into fractions of two sizes, with subsequent polishing and four-stage cleaning, and no further milling required in the cleaning circuit.

The product will be dewatered, dried and screened into saleable size fractions. The flow sheet is optimised for a high yield of large flakes; however, it could be easily modified to get higher carbon content by flotation if required. There is potential to extend the forecast mine life beyond 18 years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 10% discount rate, of $211-million and an internal rate of return of 38.9%, with a 3.4-year payback.

Value
Capital costs have been estimated at $88.9-million.

Duration
The project will take about 19 months to complete.

Latest Developments
Kibaran has produced battery-grade graphite at its Epanko project using a graphite purification method that is considered environment friendly.

The new process uses simple acids that are readily available in Tanzania, and does not use hydrofluoric acid, which is currently used by all producers of battery spherical graphite.

The ecofriendly production process supports the high environmental standards that the company has set for the Epanko project, and meets the International Finance Corporation principles and the World Bank Group standards.

Kibaran MD Andrew Spinks has said that the new process will assist the company securing a large portion of the battery graphite market.

“It is very clear that growth for battery spherical graphite is increasing at a greater rate than expected. The company’s feasibility study for the production of battery-grade graphite will be revised, given the increased demand,” Spinks has added.

The feasibility study for the production of battery spherical graphite is separate from the recently reported 60 000 t/y BFS at Epanko, which has been the catalyst for the start of the debt financing process to develop the mine so that it can produce natural flake graphite products for the traditional graphite markets.

The spherical graphite feasibility study is targeted for completion in the fourth quarter of this year and is expected to add significant value to the Epanko project, as no value has been attributed to the sale of battery spherical graphite in the flake graphite feasibility study.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Kibaran Resources, tel +61 8 6424 9000 or email info@kibaranresources.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

ASTPM
ASTPM

Established in 1983, the ASTPM is an industry association and representative body of the welded carbon steel tube and pipe manufacturers of South...

VISIT SHOWROOM 
Columbus Stainless
Columbus Stainless

Columbus Stainless, based in Middelburg, Mpumalanga, is Africa’s only producer of stainless steel flat products. In addition, Columbus is the only...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.056 0.247s - 111pq - 2rq
Subscribe Now