Elandsfontein phosphate project, South Africa – update

Elandsfontein processing plant

Photo by Kropz

19th August 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Elandsfontein phosphate project.

Location
Saldanha Bay, in the Western Cape, South Africa.

Project Owner/s
The Elandsfontein project is held by Kropz (70%), African Rainbow Capital, or ARC (25%), and a smaller empowerment partnership (5%). Ubuntu Botho Investments forms part of the ARC structure.

Project Description
The Elandsfontein deposit is the biggest sedimentary phosphate deposit in South Africa.

The phosphate mineralisation is contained in the Varswater formation, with the phosphate occurring in phosphatised shell fragments and phosphorite pellets. The remainder of the deposit consists of silica sand and calcium oxide.

The project has an initial mine life of about 14 years and can deliver one-million tonnes a year of phosphate rock concentrate at steady state.

The processing plant will produce a final saleable concentrate to the expected specification of 68% bone phosphate of lime and about 31% phosphorus oxide using a flotation configuration of direct flotation, followed by a reverse flotation circuit.

Potential Job Creation
Not stated. 

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
Kropz has spent $120-million to bring its Elandsfontein phosphates mining and processing project into production and requires an additional $16-million to cover its augmentation.

Planned Start/End Date
While the project was first scheduled to start producing phosphate in 2018, it reported first production of phosphate rock concentrate only on March 18 this year.

The Elandsfontein project has been plagued by various delays since October 2017, when its water-use licence was contested by an environmental protection group. Other challenges have included changes to its processing plans and Covid-19-related delays.

Latest Developments
Kropz has reported a delay in the ramp-up of operations at the Elandsfontein phosphate mine, owing to unexpected ore variability.

The mining rates and associated delivery of ore to the plant from the current mining area have been compromised because of the presence of competent banks of hard material within the orebody that were previously unknown.

Kropz has said this material cannot be mined using free-digging methods and, therefore, necessitates the company’s first testing the mechanical breakage of the material using new equipment and identifying alternative mining methods.

The company has also started with drilling activity to assess the impact of this hard material on the future mine plan of Elandsfontein.

Once this drilling is complete, Kropz will publish a revised mineral resource estimate, if necessary.

The delay in ramp-up of operations at the already delayed mining operations requires funding of R70-million, of which R13.5-million will be drawn down from Kropz’s existing conditional convertible equity facility with shareholder ARC Fund, marking the full-drawdown of R177-million since the facility was announced in May.

Kropz will also draw down R60-million from a R121-million bridge loan facility it agreed with ARC earlier in August.

The company is exploring further funding options with ARC to fund any additional working capital requirements for Elandsfontein through to positive cash flow.

Key Contracts, Suppliers and Consultants
DRA (engineering, procurement and construction management); Minopex (processing plant operation); and VDM Transport.

Contact Details for Project Information
Kropz, tel +27 21 930 0927 or email info@kropz.com.

Edited by Creamer Media Reporter

Comments

Showroom

SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
14th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.226 0.287s - 95pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: