Dougou potash project, Republic of Congo

31st August 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Dougou potash project.

Location
Republic of Congo (RoC).

Client
Elemental Minerals.

Project Description
The project forms part of the larger Sintoukola permit in the Republic of Congo.
Production at the Dougou deposit will be undertaken in three distinct project phases:
• Phase 1 – 400 000 t/y at a K60 potassium concentration of muriate of potash (MoP), (0% granular).
• Phase 2 – 800 000 t/y at a K60 MoP (67% granular).
• Phase 3 – 1.2-million tonnes a year K60 MoP (89% granular).

The scoping study completed on the project in 2015 envisages a solution mining operation. Water is pumped down a well to dissolve the carnallite, resulting in the production of a potassium, magnesium and sodium mineralised brine. This brine is continuously displaced by further pumping and transferred to the brine-processing plant for processing into an MoP product. To increase potassium chloride content in the brine, a hot-solution mining operation is planned using dual-well caverns, with a cavern radius of about 50 m and 70 m between the cavern wells.

Phase 1 production will comprise 12 operating caverns. To maintain steady-state production, 2.5 caverns a year have to be mined out, requiring the drilling of five new solution mining wells a year.

Completing the expansion of the full Phase 3 operation will increase the number of operating caverns to 22 in Phase 2 and to 32 in Phase 3, with five and 7.5 caverns respectively being depleted a year. The pipeline network required for the solution mining operation has been designed for a 400 000 t/y operation and will be duplicated for each subsequent production phase.

The brine produced will be processed at a centrally located process plant facility. The processing concept will continually add carnallite (produced at a later stage) to the incoming brine, which will result in the precipitation of halite and sylvite. The solid slurry is separated from the brine and processed using hot leaching and potassium chloride crystallisation to produce a K60 product.

The K60 product is dried and partially compacted during phases 2 and 3 before being transported to the storage facility. The brine from the carnallite decomposition is evaporated to produce carnallite, which is recycled to the carnallite decomposition stage. The remaining magnesium chloride brine and solid sodium chloride will be disposed into deep injection wells or mined-out caverns.

It is planned that phases 2 and 3 will each have installed compaction capacity of 532 000 t/y to produce an increasingly larger volume of granular product in each phase. The process has a conservative recovery ratio of 90% of potassium chloride from the incoming brine, transformed to product. It is planned that full core dissolution and process testwork will be undertaken in the next study phase.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 10% discount rate, of $880-million and an internal rate of return of 21.67%.

Value
The project has an unleveraged Phase 1 capital expenditure of $429.68-million.
Phase 2 capital expenditure is estimated at $450.93-million while Phase 3 is estimated at $422.77-million.

Duration
It is expected that Phase 1 construction will take about two years, with preparation of the first-solution mining wells taking place in the second year. First production is expected in the second half of 2019.

Phase 2 will start production five years after Phase 1.

Phase 3 will start production three years after Phase 2.

Latest Developments
Potash developer Kore Potash has received environmental- and social-impact assessment (Esia) approval for its Dougou mining licence.

Approval of the assessment is a prerequisite to start construction of a mining project in the RoC.

The Esia authorises the development of the potential mining project at the Dougou carnallite deposit and could be extended in future to include the Dougou extension sylvinite deposit.

Permitting for the development of the Dougou deposits allows for using potash from these deposits to increase the production rate or extend project life at the nearby Kola project, which is undergoing a definitive feasibility study (DFS).

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Elemental Minerals (South Africa), tel +27 11 469 9140.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
ECG Engineering
ECG Engineering

ECG provides specialised electrical engineering services to the Mining, Utilities, Materials Handling and Industrial industries, with extensive and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.05 0.829s - 111pq - 2rq
Subscribe Now