https://www.miningweekly.com

DiamondCorp signs beneficiation JV as Lace mine ramp-up advances

8th November 2013

By: Natalie Greve

Creamer Media Contributing Editor Online

  

Font size: - +

JSE-listed DiamondCorp subsidiary Lace Diamond Mines (LDM) has signed a diamond beneficiation joint venture (JV) agreement with Johannesburg cutting and polishing factory Distinctive Choice.

Under the terms of the JV, LDM has the option of processing some of the larger, high-quality diamonds that fall outside the offtake agreement with Tiffany & Co subsidiary Laurelton Diamonds.

“Of those diamonds that are selected for beneficiation, profits over and above the reserve price of the rough diamond are to be shared equally between the two parties,” DiamondCorp said in a statement last week.

In January, the Southern Africa-focused company agreed to a term loan of $6- million with Laurelton in exchange for an offtake agreement for diamond production from its flagship Lace mine, in the Free State.

The company reported that the first stone manufactured under the JV was an 8.36 ct white diamond, which was recovered from the dumps prior to the Laurelton agreement.

“From this diamond, three brilliant cut diamonds are being manufactured and the colour has improved during polishing. The largest stone is a 2.02 ct internally flawless diamond with no fluorescence, which has been sold for $68 000,” chair- person Euan Worthington commented.

LDM’s profit share on this stone alone had increased the return to 185% of the reserve price.

The company held that, over the life of the mine, the beneficiation JV had the potential to provide LDM with significant additional income, providing critical insight into the performance of Lace diamonds during polishing and assisting with beneficiation targets under the country’s Mining Charter.

The company further reported that the ramp-up at Lace was on schedule and within budget, with underground tunnel development currently 11% complete.

Until now, underground development had been limited to two crews operating three shifts, while blasting of the temporary vent raise, which bypassed the blockage in the vertical shaft, was completed.

“With the completion of this vent raise and the installation of surface exhaust fans, multiblast conditions now exist underground and the rate of develop- ment can increase to more than double the current rate of 200 m a month,” Worthington said.

The underground mining fleet continued to provide over 90% availability, with opera- ting costs running at 87% of budget.

The mining fleet rebuild costs were running at 95% of budget, with the last of the dump trucks and underground loaders (LHDs) required to achieve maximum underground development rates cur- rently being assembled in the workshop and scheduled to be commissioned by year-end.

Worthington noted that, with the completion of these two 20 t dump trucks and two LHDs, the full development and pro- duction fleet of five trucks, five LHDs and four face drilling rigs would be in place.

“In addition, an order has been placed with Sandvik for a new long-hole drilling rig required for drilling the undercut levels of the block cave. This drilling rig is scheduled for delivery in the second half of next year and the rand:euro exchange rate has been fixed,” he said.

Meanwhile, the new life-of-mine boxcut was completed in September and development of the twin declines from the base of the ramp has started.

Steel sets for reinforcing the portal area are now being installed, with the design and detailed drawings for the underground conveyor belts system on schedule and within budget.

Fabrication of the first leg of the conveyor belt to be installed is 95% complete and installation is about to begin. Procurement and exchange rate protection on all long-lead-time and imported items is 100% complete.

In addition, the 1.2-million- tonne-a-year dense media separation plant at Lace was successfully recommissioned during August, with material from the three-million tonnes of tailings remaining from mining activities which took place between 1902 and 1931.

The refurbished plant will now allow “seamless” transition from tailings retreatment to the processing of kimberlite from underground devel- opment.

Further, as a result of an increase in the bottom screen cut of the plant, the diamonds now being recovered are coarser in size distribution and are, therefore, expected to fetch a higher average price per carat than the diamonds pre- viously recovered from tailings.

“To confirm these figures, the company has postponed the first sale of tailings diamonds until after this month.

“While the sales revenue generated from these first parcels is not material to the overall Lace development budget, it will give management confidence that the tailings optimisation has the potential to significantly improve operating margins on this activity, which was previously expected to operate at only a small profit margin,” Worthington noted.

Plans are also in place to increase tailings throughput to more than 150 000 t a month in the first half of 2014 by intro- ducing in-pit screening.

“If recoveries are in the order of five carats per hundred tons, the in-pit screening has the potential to increase production to 7 500 ct a month, which will allow a significant proportion of the tailings to be retreated prior to the underground achieving full production,” he said.

The Lace mine is due to start production in the first half of 2015.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 
Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.048 0.809s - 110pq - 2rq
Subscribe Now