Name of the Project
Cullinan processing plant project.

Location
Gauteng, South Africa.

Client
Petra Diamonds (74%), Kago Diamonds (14%) and the Itumeleng Petra Diamonds Employee Share Trust (12%).

Project Description
Petra Diamonds has built a modern, fit-for-purpose processing plant at Cullinan, with a throughput capacity of six-million tonnes a year.

The new plant is expected to improve the recovery of the full spectrum of diamonds, thereby increasing the volume of stones recovered and protecting large stones from breakage. It will also improve the efficiency of the material flow, thereby significantly lowering operating costs and reducing the mine’s environmental footprint.

The new plant incorporates:
• autogenous milling – a gentler recovery process that breaks down ore using attrition rather than crushing, thereby better protecting the large, high-value stones for which the Cullinan mine is known;
• high-pressure grinding rolls technology – a gentler liberation technique incorporating interparticle crushing, thereby moving away from high-impact cone crushing; and
• XRF X-ray technology to replace conventional dense-media separation plants to treat coarser +12 mm material.

The new plant replaces the old plant, which was originally commissioned in 1947, thereby reducing the processing footprint at Cullinan from about 27 ha to an estimated 4 ha, with the associated reduction of engineering infrastructure deployed, including an expected reduction in the number of conveyor belts used from 151 (spanning 15 km) to 22 (spanning 3 km).

The new plant is expected to yield a saving of between R20/t and R25/t in processing costs, owing to increased energy efficiency and improved water consumption, as well as reduced circulation and maintenance requirements.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an internal rate of return of 25%, with a payback of about three years.

Value
The project is estimated at R1.65-billion to implement.

Duration
The new plant was commissioned during the fourth quarter of the 2017 financial year.

Latest Developments
All components of the Cullinan plant are now fully operational, with ramp-up and optimisation activities ongoing; the plant is expected to achieve nameplate capacity of six-million tonnes a year during the second half of the 2018 financial year.

Key Contracts and Suppliers
MDM Engineering (front-end engineering design), now part of Amec Foster Wheeler.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Petra Diamonds, email info@petradiamonds.com.
 

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Lilak Aluminium
Lilak Aluminium

For over 15 years, Lilak Aluminium, a trusted leader in architectural extrusion supply, has delivered excellence to businesses like yours.

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.043 0.851s - 111pq - 2rq
Subscribe Now