Name of the Project
Cullinan processing plant project.

Location
Gauteng, South Africa.

Client
Petra Diamonds.

Project Description
Petra Diamonds plans on building a modern, fit-for-purpose processing plant at Cullinan, with a throughput capacity of six-million tonnes a year.

The new plant is expected to improve the recovery of the full spectrum of diamonds, thereby increasing the volume of stones recovered and the protection of large stones from breakage.

It will also improve the efficiency of the material flow, thereby significantly lowering operating costs.

The new plan will incorporate:
• autogenous milling – a gentler recovery process that breaks down ore using attrition rather than crushing, thereby better protecting the large, high-value stones for which the Cullinan mine is known;
• high-pressure grinding rolls technology – a gentler liberation technique incorporating interparticle crushing, thereby moving away from high-impact cone crushing; and
• XRF X-ray technology to replace conventional dense-media separation plants to treat coarser +12 mm material.

In addition to the benefits of large stone recoveries, the improved diamond liberation technologies outlined above are expected to lead to an increase of about 10% in the overall grade achieved at Cullinan.

Further, the new plant will reduce the processing footprint at Cullinan from about 26 ha to an estimated 5 ha, with the associated reduction of engineering infrastructure deployed, including an expected reduction in the number of conveyor belts used from 151 (spanning 15 km) to 22 (spanning 3 km).

The new plant is expected to yield a saving of between R20/t and R25/t in processing costs, owing to increased energy efficiency and improved water consumption, as well as reduced circulation and maintenance requirements.

No impact on current daily operations or throughput at Cullinan is expected while the new plant is being constructed.

Jobs to be Created
Not stated.

Net Present Value/Internal Rate of Return
The project has an internal rate of return of 25%, with a payback of about three years.

Value
The project will cost about R1.65-billion to implement.

Duration
The new plant is expected to be commissioned and fully operational in the fourth quarter of the 2017 financial year.

Latest Developments
The construction of the new Cullinan Plant is progressing well and in line with expectations.

Commissioning of the new plant is planned to start in the third quarter of 2017 and is expected to be complete and fully operational by the fourth quarter.

Key Contracts and Suppliers
MDM Engineering (front-end engineering design).

On Budget and on Time?
The project is on time and within budget.

Contact Details for Project Information
Petra Diamonds, email info@petradiamonds.com.
MDM Engineering, tel +27 11 993 4300, fax +27 11 886 9306 or email info@mdm-engineering.com
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
ECG Engineering
ECG Engineering

ECG provides specialised electrical engineering services to the Mining, Utilities, Materials Handling and Industrial industries, with extensive and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.042 0.761s - 111pq - 2rq
Subscribe Now