Corruna Downs iron-ore project, Australia
Name of the Project
Corruna Downs iron-ore project.
Location
The project is located 40 km from Atlas Iron’s Mt Webber project, in the Pilbara region of Western Australia.
Client
Atlas Iron.
Project Description
The Corunna project has mineral resources of 64.1-million tonnes grading 57.2% iron. The ore reserve is estimated at 21.1-million tonnes grading 57% iron.
A definitive feasibility study (DFS) has shown the project to have the potential to deliver four-million tonnes a year of lump and fines direct-shipping iron-ore over an initial mine life of five to six years.
Mining at Corunna Downs is expected to be undertaken using a proven mining contractor to mine four openpits using conventional drill-and-blast, truck-and-excavator, and load-and-haul mining methods.
The envisaged processing plant is a semimobile, dry crush and screen plant, typical of those at other Atlas operations. The plant will produce a minimum of four-million tonnes a year of lump and fines, and be owned and operated by a contractor. The plant, run-of-mine and product yard will be located at the base of the Corunna Range.
Product will be hauled from the mine to Utah Point by road train using a haulage contractor. The DFS assumes road trains will travel from the mine to the outskirts of Marble Bar, at which point they will meet the Marble Bar road and continue into port along existing sealed roads.
Jobs to be Created
Not stated.
Net Present Value/Internal Rate of Return
Not stated.
Value
The initial capital expenditure, based on a production capacity of up to five-million tonnes a year, is estimated at between A$47-million to A$53-million, including contingency.
Duration
Subject to Atlas making an investment decision in the March quarter of this year, first ore on ship from the Corunna project is targeted for the March 2018 quarter.
Latest Developments
A decision on whether the Corunna project will proceed to development is expected to be made by the Atlas board in the March 2017 quarter, and will be subject to achieving a satisfactory funding solution.
Atlas has indicated that it will continue to progress the approvals for the Corunna project during the March quarter at minimal cost.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Atlas Iron, tel +61 8 6228 8000, fax +61 8 6228 8999 or email atlas@atlasiron.com.au.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation