Commissioning starts at Coburn
PERTH (miningweekly.com) – First ore has been processed in the wet concentrator at the Coburn mineral sands project, in Western Australia.
ASX-listed Strandline Resources on Wednesday said that while commissioning of the wet concentrator was under way, construction teams remained focused on finalising the downstream mineral separation plant (MSP) and the remaining support infrastructure.
“The team has overcome some well-documented challenges in the mining and construction industry and has achieved this success with zero lost-time or medical treatment injuries recorded to date,” said Strandline MD Luke Graham.
“With ore commissioning and tuning of the wet concentrator plant underway, we are now working to accumulate a stockpile of heavy mineral concentrate ahead of our first shipment.
“At the same time, the construction emphasis is on completion of the MSP and remaining project infrastructure.”
Strandline remains on track for first heavy mineral concentrate shipment for later this quarter.
Coburn has an ore reserves of 523-million tonnes and an initial mine life of 22.5 years at a planned average mining rate of 23.4-million tonnes a year, with the potential to extend its mine life to more than 37 years.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation