Climate change must be considered when granting water use licences, says Water Tribunal

5th August 2020

By: Simone Liedtke

Creamer Media Social Media Editor & Senior Writer

     

Font size: - +

A landmark decision by the Water Tribunal confirms that water licensing authorities must consider the impacts of climate change when deciding whether or not to grant water use licences for new coal-fired power stations.

In a decision handed down on July 21, the tribunal upheld an appeal against the setting aside of two water use licences granted by the Department of Water Affairs and Sanitation (DWS) to Acwa Power for the development of a new coal-fired power station, Khanyisa.

The tribunal found that the water use licence application was “procedurally flawed”, but also that the licensing authority “had not adequately weighed up the impact of climate change on water security in the region”.

Centre for Environmental Rights attorney Michelle Koyama says the tribunal's decision means that, when considering a water use licence application for a coal power plant, the DWS “must consider the impacts of climate change on water when deciding whether or not the project will amount to the efficient and beneficial use of water in the public interest”.

Prior to this, she adds, there was no explicit requirement to include the impacts of climate change when considering factors relevant to the decision to issue licences under the National Water Act.

The tribunal has directed Acwa Power to rectify the procedural flaws, re-advertise the application and conduct the public participation process by September 21.

This will affect its preferred bidder status in the 2014 Coal Baseload Independent Power Producer Procurement Programme, as a valid water use licence is required for the project to reach commercial and financial close.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.073 0.111s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: