https://www.miningweekly.com
Copper|Flow|Gold|Mining|PROJECT|Flow
Copper|Flow|Gold|Mining|PROJECT|Flow
copper|flow-company|gold|mining|project|flow-industry-term

Cascabel ‘no ordinary mining asset’, says SolGold as it unveils PFS

An image of the project area around Cascabel in Ecuador

The Cascabel project area in Ecuador

20th April 2022

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Dual-listed SolGold on Wednesday published a prefeasibility study (PFS) for its Cascabel project, in Ecuador, outlining plans for a multi-decade, low-cost copper producer that could help establish Ecuador as the next copper frontier.

Cascabel would produce an average of 132 000 t/y of copper, 385 000 oz/y of gold and one-million ounces a year of silver, or 212 000 t/y of copper-equivalent, with peak copper output of 210 000 t/y.

With an initial life-of-mine all-in sustaining cost (AISC) of $0.06/lb of copper, Cascabel would be “well within” the first decile of the copper industry cost curve.

Once the project reached nameplate capacity of 330 000 t/y of copper-equivalent over an initial five years, the mine would operate at an average negative AISC of $1.38/lb.

MD and CEO Darryl Cuzzubbo commented that the PFS demonstrated that Cascabel was “no ordinary mining asset”.

“This project is economically attractive and based upon assumptions that we believe can be delivered upon. There is further upside that will be explored over the coming months and the next phase of the project as we seek the necessary government approvals and move into early works and execution.”

The PFS estimates an aftertax net present value (NPV) of $2.9-billion, an internal rate of return (IRR) of 19.3% and a 4.7 year payback period from the start of processing.

At current spot commodity prices, the aftertax NPV would be $4.1-billion and the IRR 23.4%.

On average, Cascabel will generate aftertax free cash flow of $740-million, peaking at more than $1.6-billion, and earnings before interest, taxes, depreciation and amortisation of nearly $1.2-billion a year, peaking at $2.4-billion a year.

SolGold chairperson of the Cascabel project steering committee, Keith Marshall, explained that the PFS focused on the ‘right-sizing’ of the project, with the objective of reducing the technical and execution risk.

“It also provides a straightforward approach to mining the deposit that optimises selectivity without compromising any of the resource and maintaining optionality.

“I am confident that the study lays the solid groundwork for the next steps in the Cascabel project. I am particularly looking forward to progressing the study work and being able to expand our operational activities in Ecuador.”

The Cascabel project has an initial mineral reserve estimate of 558-million tonnes, with 0.58% copper, 0.52 g/t gold and 1.65 g/t silver for 3.3-million tonnes of copper, 9.4-million ounces of gold and 30-million ounces of silver.

SolGold’s share price gained 3% in London on Wednesday, trading at 35.19p a share.

Edited by Creamer Media Reporter

Comments

Showroom

ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

PGMs and green hydrogen make headlines
PGMs and green hydrogen make headlines
19th April 2024
Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.238 0.275s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: