Canada Lithium on track for first shipment in March

31st January 2013

By: Henry Lazenby

Creamer Media Deputy Editor: North America

  

Font size: - +

TORONTO (miningweekly.com) – Quebec project developer Canada Lithium on Thursday said commissioning of the mineral processing sections of the process plant continued on schedule with concentrate being produced on a regular basis and final electrical work and software programming being undertaken on the lithium carbonate circuits.

Canada Lithium said there would be a number of site visits by its offtake partners and various battery manufacturers as its approached the first shipment of lithium carbonate under the five-year Tewoo offtake agreement at the end of March.

The 20 000 t/y lithium carbonate processing plant is scheduled to complete ramp-up to full production by the fourth quarter this year.

Further, the company expected the final drawdown of C$25-million of the C$75-million debt facility from the banking syndicate to take place during February and March.

The company’s TSX-quoted stock traded down 1.15% apiece at 86 Canadian cents apiece on Thursday; however, it had gained 67.31% in value over the last six months.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.047 0.933s - 128pq - 2rq
Subscribe Now