https://www.miningweekly.com

Camino Rojo oxide project construction continuing apace

23rd March 2021

By: Creamer Media Reporter

     

Font size: - +

Dual-listed Orla Mining is on track to pour first gold from the Camino Rojo oxide project, in Mexico, by the end of the year, president and CEO Jason Simpson said on Monday, in a construction update.

He reported that detailed engineering and procurement were well-advanced, positioning the project team for a successful execution.

Orla has selected a mining contractor and expects mining activities to start in the second quarter.

“Construction ramped up in the fourth quarter and we are focused on the critical path activities as we target first pour by the end of year," said Simpson.

Current construction activities include earthworks, installation of the camp and offices, drilling of back-up water wells, and site fence erection. Process pond and reclaim tunnel areas are being excavated and foundations are being prepared for the Merrill Crowe plant, crusher, camp, as well as ancillary buildings.

Flora and fauna relocation is 97% complete while clearing and grubbing is 91% complete. The 33-kV power line to site was approved by the Mexican federal electricity commission in 2020 and construction is currently 73% complete.

While construction at the oxide project is continuing apace, Orla is advancing multiple development scenarios on the Camino Rojo sulphide project, targeting a completed preliminary economic assessment by year-end.

The company reported that a 6 000-m oriented core drilling programme began on the large sulphide resource at the Camino Rojo deposit in the fourth quarter of 2020. The objective of the programme is to generate additional information regarding the continuity and geometry of the higher-grade mineralisation and provide new material for geotechnical and metallurgical studies. The drilling programme is about 80% complete.

In Panama, work is also under way on the Cerro Quema prefeasibility study, which is expected to be completed by the second quarter.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

ASTPM
ASTPM

Established in 1983, the ASTPM is an industry association and representative body of the welded carbon steel tube and pipe manufacturers of South...

VISIT SHOWROOM 
Virtual Gas Network (Pty) Ltd
Virtual Gas Network (Pty) Ltd

Virtual Gas Network supplies compressed natural gas via a virtual gas distribution network.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.045 0.857s - 110pq - 2rq
Subscribe Now