Bullabulling gold project, Australia
Name and Location
Bullabulling gold project, Australia.
Client
Bullabulling Gold.
Project Description
The Bullabulling project is located 60 km west of Kalgoorlie, in Western Australia, and a has total resource of 104.5-million tons grading 0.99 g/t of gold.
A prefeasibility study (PFS) completed on the project has concluded that it is technically and financially viable.
The PFS envisages the development of a 7.5-million-ton-a-year openpit mining operation with a conventional carbon-in-leach facility.
Gold production of 1.95-million ounces is forecast over a mine life of 10.5 years.
Principal project infrastructure includes access roads, a 142-person accommodation facility, a borefield, a tailings storage facility and an electrical power supply.
Value
Total capital expenditure is estimated at $326.4-million.
Duration
A development decision is expected by the end of 2013.
Engineering, procurement and construction of the mine, plant and associated infrastructure have been estimated at 21 months, leading to gold production starting at the beginning of the fourth quarter of 2015.
Mining will start six months prior to production to provide waste rock for the construction of the run-of-mine ore pad and tailings storage facility; in addition, about 160 000 t of ore will be produced during this period to facilitate plant commissioning.
A three-month ramp-up period has been allowed for the plant, during which time an estimated 1.4-million tons of ore will be processed, with 50 000 oz produced.
Latest Developments
Work will start immediately on the definitive feasibility study (DFS).
A range of specific opportunities to optimise the project and enhance financial performance has been identified for evaluation in the DFS.
Completion of the DFS and a development decision are expected to be made by the end of 2013.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Bullabulling Gold, tel +61 8 9386 4086 or fax +61 8 9389 8327.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation