Buck Creek coal mine complex project, US
Name of the Project
Buck Creek coal mine complex project.
Location
The Buck Creek mine complex is located in the Western Kentucky region of the Illinois basin, which is one of the most prolific coal-producing regions in the US.
Project Owner/s
Paringa Resources.
Project Description
The coal mining complex includes the staged, modular development of the 2.8-million-tonne-a-year Poplar Grove and 3.8-million-tonne-a-year Cypress mines.
An expanded bankable feasibility study (BFS) completed on Poplar Grove in March has incorporated a second coal seam to the mine – the Western Kentucky No 11 (WK 11) coal seam – resulting in a 56% increase in mine production to 2.8-million tonnes a year. The original BFS, which included the Western Kentucky No 9 (WK 9) coal seam, considered a 1.8-million-tonne-a-year operation.
Access to the WK 9 seam will be through a low-cost boxcut excavation followed by three decline drifts excavated using continuous mining equipment.
Paringa will access the WK 11 seam from the northern limb of Poplar Grove’s mine plan by 2020 through an incline, excavated using continuous mining equipment.
In 2033, Paringa will access the WK 11 seam from the southern limb of Poplar Grove’s mine plan.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The combined net present value (NPV) of both mines, at an 8% discount rate, has been estimated at $655-million. On a standalone basis, the NPV of the projected cashflows from the initial Poplar Grove mine has been estimated at $310-million at an 8% discount rate, with an internal rate of return of 42%.
Capital Expenditure
The expanded BFS has estimated total capital expenditure (capex) for the initial construction of Poplar Grove at $44.7-million. Capital for construction of the WK 11 incline and vertical shafts is estimated at $15.8-million, which will be funded from Poplar Grove’s operating cashflow.
Capex at the Cypress mine has been estimated at $101.8-million.
Planned Start /End Date
Construction of the Poplar Grove mine started in August 2017. First coal is expected 12 months from the start of construction.
Latest Developments
Paringa Resources has continued to ramp up production from its US operations during the three months to September.
Run-of-mine production from its Poplar Grove operation, in western Kentucky, increased to 277 600 t during the September quarter, up from the 95 000 t produced in the previous quarter, while saleable coal production increased to 143 300 t, from 26 700 t.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
The project remains on track.
Contact Details for Project Information
Paringa Resources, MD and CEO Grant Quasha, tel +61 8 9322 6322 or email gquasha@paringaresources.com.
Buck Creek coal mine complex project.
Location
The Buck Creek mine complex is located in the Western Kentucky region of the Illinois basin, which is one of the most prolific coal-producing regions in the US.
Project Owner/s
Paringa Resources.
Project Description
The coal mining complex includes the staged, modular development of the 2.8-million-tonne-a-year Poplar Grove and 3.8-million-tonne-a-year Cypress mines.
An expanded bankable feasibility study (BFS) completed on Poplar Grove in March has incorporated a second coal seam to the mine – the Western Kentucky No 11 (WK 11) coal seam – resulting in a 56% increase in mine production to 2.8-million tonnes a year. The original BFS, which included the Western Kentucky No 9 (WK 9) coal seam, considered a 1.8-million-tonne-a-year operation.
Access to the WK 9 seam will be through a low-cost boxcut excavation followed by three decline drifts excavated using continuous mining equipment.
Paringa will access the WK 11 seam from the northern limb of Poplar Grove’s mine plan by 2020 through an incline, excavated using continuous mining equipment.
In 2033, Paringa will access the WK 11 seam from the southern limb of Poplar Grove’s mine plan.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The combined net present value (NPV) of both mines, at an 8% discount rate, has been estimated at $655-million. On a standalone basis, the NPV of the projected cashflows from the initial Poplar Grove mine has been estimated at $310-million at an 8% discount rate, with an internal rate of return of 42%.
Capital Expenditure
The expanded BFS has estimated total capital expenditure (capex) for the initial construction of Poplar Grove at $44.7-million. Capital for construction of the WK 11 incline and vertical shafts is estimated at $15.8-million, which will be funded from Poplar Grove’s operating cashflow.
Capex at the Cypress mine has been estimated at $101.8-million.
Planned Start /End Date
Construction of the Poplar Grove mine started in August 2017. First coal is expected 12 months from the start of construction.
Latest Developments
Paringa Resources has continued to ramp up production from its US operations during the three months to September.
Run-of-mine production from its Poplar Grove operation, in western Kentucky, increased to 277 600 t during the September quarter, up from the 95 000 t produced in the previous quarter, while saleable coal production increased to 143 300 t, from 26 700 t.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
The project remains on track.
Contact Details for Project Information
Paringa Resources, MD and CEO Grant Quasha, tel +61 8 9322 6322 or email gquasha@paringaresources.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation