https://www.miningweekly.com

Buck Creek coal mine complex project, US

5th April 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Buck Creek coal mine complex project.

Location
The Buck Creek mine complex is located in the Western Kentucky region of the Illinois basin, which is one of the most prolific coal-producing regions in the US.

Client
Paringa Resources.

Project Description
The coal mining complex includes the staged, modular development of the 2.8-million-tonne-a-year Poplar Grove and 3.8-million-tonne-a-year Cypress mines.

An expanded bankable feasibility study (BFS) completed on Poplar Grove in March has incorporated a second coal seam to the mine – the Western Kentucky No 11 (WK 11) coal seam – resulting in a 56% increase in mine production to 2.8-million tonnes a year. The original BFS, which included the Western Kentucky No 9 coal seam, considered a 1.8-million-tonne-a-year operation.

Access to the WK 9 seam will be through a low-cost boxcut excavation followed by three decline drifts excavated using continuous mining equipment.

Paringa will access the WK 11 seam from the northern limb of Poplar Grove’s mine plan by 2020 through an incline, excavated using continuous mining equipment.

In 2033, Paringa will access the WK 11 seam from the southern limb of Poplar Grove’s mine plan.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The combined net present value (NPV) of both mines, at an 8% discount rate, has been estimated at $655-million. On a standalone basis, the NPV of the projected cash flows from the initial Poplar Grove mine has been estimated at $310-million at an 8% discount rate, with an internal rate of return of 42%.

Value
The expanded BFS has estimated total capital expenditure (capex) at $44.7-million for the initial construction of Poplar Grove. Capital for construction of the WK 11 incline and vertical shafts is estimated at $15.8-million, which will be funded from Poplar Grove’s operating cash flow.

Capex at the Cypress mine has been estimated at $101.8-million.

Duration
Construction of the Poplar Grove mine started in August 2017. First coal is expected 12 months from the start of construction.

Latest Developments
Paringa Resources had delayed the first coal sales from its Poplar Grove operation by two weeks until the week of April 22.

The delay in coal sales is as a result of the decision to install the slope conveyor sooner than originally planned, as the run-of-mine (RoM) volumes being brought to the surface by underground mucking and transportation have been lower than expected, owing to a directive from the Mine Safety and Health Administration that has limited operations to one loader.

The slope conveyor being installed will have the capacity to transport up to 2 000 t/h of RoM material from the slope bottom, and will enable Paringa to further improve the planned ramp-up of production from Poplar Grove.

The company has indicated that although the first shipment of coal will be delayed, the establishment of the permanent ventilation system and operations using the mine slope conveyor will enable Paringa to start a typical underground room-and-pillar mining sequence, increasing mining advance rates and eliminating the haulage bottleneck currently limiting the mine’s production ramp-up.

The 2.8-million-tonne-a-year Poplar Grove thermal coal mine forms part of Paringa’s 16 100 ha Buck Creek complex, which also contains the 3.8-million-tonne-a-year Cypress mine, where construction is set to begin in 2019.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
The project remains on track.

Contact Details for Project Information
Paringa Resources, MD and CEO Grant Quasha, tel +61 8 9322 6322 or email gquasha@paringaresources.com.
 

 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 
Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.049 0.848s - 111pq - 2rq
Subscribe Now