Name of the Project
Broadmeadow East and Isaac River coal projects.

Location
The Broadmeadow East project is situated about 185 km south-west of Mackay, Queensland, and 25 km north-east of the major regional township of Moranbah in the central Bowen basin, in Australia.

The Isaac River project is located in the central Bowen basin, about 30 km to the east of Moranbah, in Central Queensland, Australia.

Project Owner/s
Bowen Coking Coal.

Project Description
The Broadmeadow East project has resources of 33-million tonnes, of which 10.6-million tonnes are in the measured and indicated categories. Isaac River has resources of 8.7-million tonnes, of which 8.3-million tonnes are in the measured and indicated categories.

The results of the first-stage independent scoping studies on the Broadmeadow East and Isaac River coal projects have shown a run-of-mine production target of 800 000 t/y to 1.1-million tonnes a year over a five- to seven-year life-of-mine (LoM) for Broadmeadow East, and 400 000 t/y to 600 000 t/y over a four- to five-year LoM for Isaac River.  

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
The Broadmeadow East project is expected to cost A$6- to A$8-million and the Isaac River project A$14- to A$17-million.

Planned Start/End Date
Not stated.

Latest Developments
Bowen Coking Coal is one step closer to first production after the Queensland government approved an amendment to the Broadmeadow East project’s existing environmental authority.

Alongside the existing, granted mining lease, this is the final approval required to start mining operations on site.

“The approval renders the project ‘shovel ready’ at a time when coking coal prices are rallying to record highs. We are in the final stages of our mining contractor selection process, with a target for first coal production from Broadmeadow East in the June quarter to be processed through the Fitzroy infrastructure,” Bowen Coking Coal MD and CEO Gerhard Redelinghuys says.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Bowen Coking Coal, tel +61 7 3191 8413 or email info@bowencokingcoal.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.052 0.816s - 111pq - 2rq
Subscribe Now