https://www.miningweekly.com

Boikarabelo coal project, South Africa

3rd November 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Boikarabelo coal project.

Location
Waterberg region in Limpopo, South Africa.

Client
Resource Generation (Resgen).

Project Description
The project has a 6.4-billion-tonne resource, with probable reserves of 744.8-million tonnes on 35% of the tenements under management and delineated to date.

The Boikarabelo coal seam is between 20 m and 30 m below the surface, allowing for low-cost, opencut mining. The seam is between 100 m and 120 m thick, with zones of varying-quality thermal and soft coking coal.

In February 2016, Resgen reported that it would implement a revised mine plan at its Boikarabelo coal mine. This followed a technical review of the geological model by its technical committee comprising in-house and external experts, who suggested that the revised mine plan could achieve a better opportunity than previously expected. The plan is based on selective mining and in-pit dumping to maximise productivity, reduce operating costs and minimise any environmental impact.

The company will also implement a project execution strategy that transfers mine construction risk through the appointment of a small number of reputable engineering, procurement and construction (EPC) contractors with substantial balance sheets, which will allow for recourse in the event of failure or delay.

The mine will be developed using a two-phased approach to limit upfront capital expenditure. The first phase will deliver about 15-million tonnes of run-of-mine coal a year, which will equate to about six-million tonnes of product coal. Of this, about 3.6-million tonnes will be exported and about 2.4-million tonnes will be used domestically.

Phase 2, planned for 2022, will involve ramping up production to 12-million tonnes of product thermal coal.

The project includes a 48 km rail link to the existing rail network.

To expand the Boikarabelo project’s economic base, a bankable feasibility study on a 600 MW independent mine-mouth power station is being fast-tracked to operate as an approved independent power producer (IPP). Environmental and land use approvals have been obtained for a 300 MW IPP and are being revised to accommodate a 600 MW IPP.

Potential Job Creation
The project is expected to create 2 500 jobs in the construction phase and 709 full-time jobs.

Net Present Value/Internal Rate of Return
The project has an internal rate of return of 17%.

Value
The estimated capital cost for the project is $545-million.

Duration
Resgen’s black economic-empowerment subsidiary Ledjadja Coal received the Boikarabelo mining rights from the Department of Mineral Resources in April 2011. Initial construction of the mine started in the first quarter of 2013 and was scheduled for completion in September 2018. However, the mine’s expected date of first coal production has been delayed and is now expected to begin production in 2019.

Latest Developments
Resgen has made demonstrable progress on material contracts and funding for the rail link at its Boikarabelo coal mine in the three months to September 30.

The first credit approval for full funding of the link has been obtained from the Development Bank of Southern Africa.

The rail link will be built by RME, a subsidiary of Transnet Freight Rail, under a fixed-price, turnkey engineering, procurement and construction (EPC) contract.

“Progress is also being made regarding the planned 300 MW IPP [plant]. A provisional equity structure, under which the company and Ledjadja Coal will have direct equity interests, is under discussion,” the company has said.

A joint development agreement is being drafted by Resgen’s appointed legal counsel and a full technical specification of the IPP is being prepared by an independent consulting firm.

It is expected that a selection process to identify and appoint the EPC contractor will begin during the first half of 2018.

During the September quarter, the group drew down the final instalment of the working capital facility.

In addition, the group agreed with Noble Resources to extend the start of repayment of the amounts borrowed under the facility agreement from September 2017 to April 2018.

Key Contracts and Suppliers
Digby Wells Environmental (mining right application, mine-waste licence, environmental authorisation process for power plant); Sedgman (coal handling and processing plant and ancillary work packages); RCE (rail design and construction, EPC management services); NuWater (water EPCM services); EHL Energy (transmission lines), Stefanutti Stocks (preferred mining contractor), Stefanutti Stocks Road and Earthworks (rail earthworks and bridges), RNE (rail link) and Transnet Freight Rail (ballast, track and signaling).

On Budget and on Time?
First production has been delayed to 2019.

Contact Details for Project Information
Resgen, tel +27 12 345 1057, fax +27 12 345 or email info@resgen.com.au

 
 
 
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Kriel Occupational Health Centre
Kriel Occupational Health Centre

Occupational health services, mobile clinics, wellness campaigns, aviation.

VISIT SHOWROOM 
Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.044 0.737s - 111pq - 2rq
Subscribe Now