Block 14 gold project, Sudan

Image of Block 14 drill rig

29th October 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Block 14 gold project.

Location
The Nubian desert, in northern Sudan.

Project Owner/s
Orca Gold (70%).

Project Description
A revised feasibility study on Block 14 has shown a material improvement in the operating costs of the project. The project has probable reserves of 79.94-million tonnes grading 1.11 g/t for 2.85-million ounces of gold.

The revised feasibility study envisages a conventional truck-and-shovel openpit operation feeding a mineral processing circuit incorporating primary crushing, semiautogenous grinding and ball mill grinding, followed by carbon-in-pulp leaching, stripping and electrowinning.

The project has a mine life of 13.6 years, with life-of-mine production estimated at 167 000 oz/y of gold. The project has a milling capacity of six-million tonnes a year.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 5% discount rate, of $607-million and an internal rate of return of 33.3%, with a payback of 2.9 years.

Capital Expenditure
Preproduction capital has decreased from $328-million in the November feasibility study to $321-million.

Planned Start/End Date
The project is expected to take 27 months to build.

Latest Developments
Orca remains confident that Block 14 will achieve production as scheduled, following despite news of a military coup in Sudan on October 25.

All agreements to advance the project have been signed and Orca’s decision to build the mine has not changed, with General Abdel Fattah Abdelrahman al-Burhan stating on October 26 that all commercial agreements will continue to be honoured by government.

“We are monitoring the current political situation closely and will report back as more information becomes available,” CEO Rick Clark has said.

Key Contracts, Suppliers and Consultants
Lycopodium Minerals (feasibility study).

Contact Details for Project Information
Orca Gold, tel +1 604 689 7842 or email info@orcagold.com.

Edited by Creamer Media Reporter

Comments

Projects

IMAGE OF GOLD BARS
Berg gold project, Canada
Updated 6 hours ago By: Sheila Barradas

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
14th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.177 0.229s - 91pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: