Name of the Project
Black Swan nickel operations restart project.

Location
Kalgoorlie, in Western Australia.

Project Owner/s
Poseidon Nickel.

Project Description
A bankable feasibility study (BFS) on Black Swan has proved positive.

The BFS is based on mining ore from the Black Swan disseminated openpit (serpentinite ore only) and Silver Swan and Golden Swan high-grade underground mines, supplemented with Silver Swan tailings and existing surface stockpiles (disseminated serpentinite material) and processing these feed sources through the existing concentrator and associated infrastructure.

Black Swan can produce a high-grade nickel concentrate with an estimated 15% nickel, 6% magnesium oxide and an iron:magnesium oxide ratio of 5:1, which is highly desirable for conventional nickel smelters.

The BFS envisages the refurbishment and operation of the existing plant with a processing capacity of 1.1-million tonnes a year to align with the available processing mine inventory of five-million tonnes, presenting an after development project life of four years. Over the life of the project, the Phase 1 Black Swan project will produce 200 000 t of smelter grade concentrate, averaging 15% nickel containing an estimated 30 000 t of nickel from the various feed sources, representing an average metal recovery of 68%.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of $248-million and an internal rate of return of 103% at the current Australian dollar nickel price.

Capital Expenditure
Capital expenditure is estimated at A$98.9-million.

Planned Start /End Date
If a final investment decision is made during first half 2023, concentrate production could start in early 2024.

Latest Developments
A feasibility study on the 2.2-million-tonne-a-year ore feed option to produce rougher concentrate is due for completion in the first half of 2023.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Poseidon Nickel, tel +618 6167 6600, fax +618 6167 6649 or email admin@poseidon-nickel.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.055 0.079s - 111pq - 2rq
Subscribe Now