Black Rock mine and Gloria modernisation projects, South Africa – update


Name of the Project
Black Rock mine and Gloria modernisation projects.
Location
Black Rock, in the Northern Cape, South Africa.
Project Owner/s
Assmang, which is jointly controlled by Assore and African Rainbow Minerals.
Project Description
The projects will modernise and expand the mine by increasing volume and flexibility to produce the differentiated medium- to high-grade products, which the manganese market is increasingly demanding and for which it is paying a premium, while improving efficiencies.
The project will increase overall production to about five-million tons a year of manganese, subject to rail availability and market conditions.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
Not stated.
Capital Expenditure
R2.97-billion has been approved for the project, most of it sustaining capital expenditure. Eighty-seven per cent of the approved capital for the project was spent on the Gloria project as at December 31, 2021.
The Black Rock project is estimated at R7.3-billion.
Planned Start/End Date
The Gloria project is forecast to be completed in June 2023.
Latest Developments
ARM has reported that as at December 2022, the Gloria project was 96% complete, with 95% of the approved budget of R3-billion being spent.
The Black Rock project was completed on budget and handed over to operations in September 2022.
The planned ramp-up in tonnages from the modernisation of the Gloria and Black Rock mines is constantly being reviewed to align with State-owned logistics company Transnet’s capacity allocation and market fluctuation.
Key Contracts, Suppliers and Consultants
DRA Global (engineering, procurement and construction management).
Contact Details for Project Information
Assore, tel +27 11 770 6800.
African Rainbow Minerals investor relations and corporate affairs head Jongisa Magagula, tel +27 11 779 1300, fax +27 11 779 1312 or email jongisa.magagula@arm.co.za.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation