PERTH (miningweekly.com) – Gold miner Beadell Resources on Monday warned of a delay to the start of openpit cutbacks at its Duckhead operations, at the Tucano mine in Brazil.

The miner explained that issues had arisen with third-party regulatory approvals associated with the mining concession that contained the Duckhead deposit.

The cutback was expected to contribute some 20 000 oz, at 28.7 g/t gold to Beadell’s production during 2015. However, the miner warned that any further delays could push the five-month mining duration of the cutback into the 2016 production profile.

The miner noted that its current 2015 production guidance of between 170 000 oz and 190 000 oz was dependent on a timely start to the cutback at Duckhead.

Beadell was forced to halt production at the Duckhead mine during 2014, as it introduced a new mine plan.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 
Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.054 0.937s - 111pq - 2rq
Subscribe Now