https://www.miningweekly.com

Bald Hill lithium plant, Australia

23rd February 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Bald Hill lithium plant.

Location
The project area is located 50 km south-east of Kambalda, in the Eastern Goldfields of Western Australia.

Client
Tawana Resources and Alliance Mineral Assets Limited (AMAL).

Project Description
The project comprises four mining leases, one mining lease application, 12 exploration licences, eight prospecting licences and one general purpose lease totalling 790 km.

A July 2017 prefeasibility study (PFS) confirmed the technical and financial viability of a low-capital-cost, 1.2-million-tonne-a-year lithium dense-media separation (DMS) circuit, adjacent to the existing tantalum processing facility at Bald Hill.

The PFS estimates initial production of 155 000 t/y of spodumene concentrate from the DMS and 260 000 lb/y of tantalum pentoxide from the tantalum processing facility. Further feasibility work is being undertaken on a lithium fines circuit to treat stockpiled fines and middlings, which has the potential to add to production.

Potential Job Creation
About 200 people will be on site during the peak construction period.

Net Present Value/Internal Rate of Return
The project has an expected internal rate of return of 185%.

Value
A$42.20-million.

Duration
The first shipment of lithium concentrate is scheduled for March 2018.

Latest Developments
Tawana Resources and Alliance Minerals have started commissioning the DMS circuit at the Bald Hill project.

First spodumene concentrate is expected as soon as ore is fed to the DMS circuit in early March.

Dry commissioning has started and is expected to continue until late February, while wet commissioning was scheduled to start on February 21.

The crushing and stockpiling of ore has started and the motor control centre and low-voltage switch room have also been commissioned.
Ore feed to the DMS is expected in early March, subject to wet commissioning.

Key Contracts and Suppliers
Primero Group (EPC).

On Budget and on Time?
The project is on track for commissioning to start in the first quarter of 2018.

Contact Details for Project Information
Tawana investor relations, tel +61 8 9489 2600 or email admin@tawana.com.au.
 
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Rio-Carb
Rio-Carb

Rio Carb is an OEM (Original Equipment Manufacturer) of R-C700 Chromium Carbide (CrC) alloy clad wear plates and pipes used for heavy materials...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.051 0.911s - 111pq - 2rq
Subscribe Now