Aurora gold project, Guyana
Name and Location
Aurora gold project, Guyana.
Client
Guyana Goldfields.
Project Description
The Aurora gold project contains proven and probable reserves of about 3.47-million ounces of gold, with a grading of 2.74 g/t gold.
An updated feasibility study on the project indicates that the openpit and underground mining operations are economically robust, with substantial upside potential.
The updated study envisages staged gold production, with initial openpit production at Rory’s Knoll supplying ore to the mill at a rate of 5 000 t/d. Rory’s Knoll will be mined using the open-benching and sublevel-retreat mining methods through a decline access with truck haulage, while the satellite openpits are mined concurrently. During this phase, mill capacity will increase to 10 000 t/d for five years. Thereafter, mining will continue underground for nine years, with the mill operating at 5 300 t/d.
The study estimates that 3.29-million ounces of gold will be produced over an initial 17-year mine life.
Value
$205-million.
Duration
Production is expected to begin in 2015.
Latest Developments
Guyana Goldfields expects to explore the existing potential to incorporate into the mine plan previously defined resources contained below the pit shell at Aleck Hill and below the Rory’s Knoll underground mine design.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Guyana Goldfields VP: corporate communications Jacqueline Wagenaar, tel +1 416 628 5936 ext 2295 or
email jwagenaar@guygold.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation