Aureus advances New Liberty project
JOHANNESBURG (miningweekly.com) – Construction of TSX- and Aim-listed Aureus Mining’s New Liberty gold project, in Liberia, remained on track, with first gold expected during the first quarter of 2015.
The New Liberty engineering and construction programme is progressing according to schedule, with the company having awarded the engineering, procurement and construction management design and construction services contract to DRA Mineral Projects.
The structural, mechanical, platework and piping supply contract had also been awarded, with first steel planned from the fabrication works before year-end.
"Construction at New Liberty remains on schedule with significant progress made during this year. We are well positioned to continue to deliver during 2014 and achieve the first gold pour in 2015. I look forward to Aureus becoming Liberia's first commercial, and one of West Africa's newest, gold producers,” Aureus Mining president and CEO David Reading said.
The ball mill shell, which would be released from fabrication in December and shipped to the New Liberty site by the second quarter of 2014, had passed its final inspection and progress was ahead of schedule. The mill ends would also be completed and released from fabrication in December.
All bush clearing had been completed for the process infrastructure, including the tailings storage facility area, and upgrade work on the Daniels Town access road bridges was under way, with one of four bridges already complete.
Further, the Marvoe Creek spillway earthworks were nearing completion, with topsoil removal and excavations under way at the holding dams.
“Civil works are advancing at the primary and secondary crusher foundations, the secondary screening building, the mill stockpile tunnel foundation, the carbon-in-leach tanks and the gold room foundations,” the company added.
Meanwhile, construction at the Camp David staff accommodation complex was on track, with junior accommodation nearing completion and senior and visitor accommodation construction under way.
“Work continues at the New Kinjor township, with building work on the church and mosque completed, and the construction of houses and the community centre ongoing.”
The company had completed the foundations for 100 of the 161 duplex housing units under construction. Two house units have been completed, with a further 20 units at an advanced stage.
Further, the two school buildings that were under construction would be ready for occupation during December.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation