Arctic project remains robust despite capital and operating cost jump

14th February 2023

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

The Arctic base and precious metals project, in Alaska, continues to be robust, even in the high inflationary environment that has seen its initial capital expenditure (capex) forecast rise by 30% to $1.12-billion.

Canada’s Trilogy Metals, which owns the Arctic project in a joint venture with Australia’s South32, on Tuesday announced the results of an updated feasibility study that describes the viability of establishing a conventional copper/zinc/lead/silver/gold mine and mill complex for a 10 000 t/d operation over a 13-year mine life.

“Arctic continues to be an extremely robust project even in a high inflationary environment. We have updated the capital and operating costs to reflect high-inflation and supply-chain challenges and yet the economics continue to stand out,” said Trilogy president and CEO Tony Giardini.

Operating costs increased by 18% from the 2020 feasibility study to $59.83/t milled, while initial capex jumped from $905.6-million in 2020 to $1.18-billion.

The latest feasibility study yielded an after-tax net present value of $1.11-billion, compared with $1.13-billion, and an after-tax internal rate of return of 22.8%, compared with 27.1% in 2020.

The 2023 feasibility study uses long-term metal prices of $3.65/lb for copper, $1.15/lb for zinc, $1.00/lb for lead, $1 650/oz for gold and $21.00/oz for silver in its economic analysis.

On average, Arctic will produce 148.68-million pounds of copper, 172.60-million pounds of zinc, 25.75-million pounds of lead, 32 538 oz of gold and 2 773 oz of silver every year.

Total life-of-mine 13-year production is projected at 1.9-billion pounds of copper, 2.2-billion pounds of zinc, 335-million pounds of lead, 423 000 oz of gold and 36-million ounces of silver.

Edited by Creamer Media Reporter

Comments

Showroom

Sandvik Mining and Rock Solutions
Sandvik Mining and Rock Solutions

Sandvik offers a wide range of loaders and trucks for underground hard rock mining, all engineered for safety, productivity and reliability in the...

VISIT SHOWROOM 
KEY360 Management Platform
KEY360 Management Platform

KEY360 Platform Technology is reputedly the world’s leading Project Management and Business Optimization Solution. Award Winning KEY360 is your...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (01/12/2023)
1st December 2023
Photo of Martin Creamer
Jupiter Mines, Copper 360 and DRDGold make headlines
1st December 2023

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.166 0.202s - 113pq - 2rq
Subscribe Now