https://www.miningweekly.com
Africa|Construction|Container|Design|Energy|Eskom|Financial|Freight|Infrastructure|Iron Ore|Power|PROJECT|rail|Renewable Energy|Renewable-Energy|Service|Solar|Steel|Terminals|Transnet|Transnet Port Terminals|Equipment|Maintenance|Products|Solutions|Infrastructure|Operations
Africa|Construction|Container|Design|Energy|Eskom|Financial|Freight|Infrastructure|Iron Ore|Power|PROJECT|rail|Renewable Energy|Renewable-Energy|Service|Solar|Steel|Terminals|Transnet|Transnet Port Terminals|Equipment|Maintenance|Products|Solutions|Infrastructure|Operations
africa|construction|container|design|energy|eskom|financial|freight|infrastructure|iron-ore|power|project|rail|renewable-energy|renewable-energy-company|service|solar|steel|terminals|transnet|transnet-port-terminals|equipment|maintenance|products|solutions|infrastructure|operations

ArcelorMittal moves ahead with 200 MW Vanderbijl renewables project, studies third-party rail access

ArcelorMittal South Africa CEO Kobus Verster

ArcelorMittal South Africa CEO Kobus Verster

9th February 2023

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

ArcelorMittal South Africa (AMSA) expects initial construction work on a 200 MW renewable-energy plant in Vanderbijlpark, Gauteng, to begin during the fourth quarter of 2023, with a feasibility study into the solution nearing completion.

The solar photovoltaic project is expected to cost R4-billion to construct and the facility will be built and operated by a special purpose vehicle (SPV) owned by AMSA and the ArcelorMittal Group, which has agreed to support the funding of the project.

The SPV will contract with the Vanderbiiljpark mill and will be funded by a combination of 20% equity and 80% debt and will supply about 40% of the plant’s electricity demand at a tariff that will be “substantially cheaper” than the Eskom tariff.

CEO Kobus Verster says the project, which will be built mainly on AMSA land adjacent to the mill and connect to the grid infrastructure already on site,  has been necessitated by ongoing unreliable electricity supply and rising tariffs and he anticipates that the investment will begin delivering “meaningful cost reduction benefits by 2024/5”.

“The decision has been made to construct one large 200 MW plant at Vanderbijlpark as this will yield the greatest operational and commercial benefit,” reported Verster, noting that it had initially been considering a 100 MW wind farm in Saldanha Bay and a 100 MW solar project at Vanderbijlpark.

“Work is also progressing on closing power purchase agreements with third-party renewable energy providers,” Verster confirmed when releasing the JSE-listed group’s results for the year ended December 31, 2022.

There is potential, for instance, to supply wheeled wind electricity from a third party to the Newcastle operation.

The investment decision has been made against the backdrop of South Africa having experienced its worst-ever year for rotational power cuts last year, when over 200 days were affected by loadshedding and energy-intensive companies such as AMSA were regularly directed to implement load curtailment. Loadshedding has continued at high stages in 2023, with cuts having been implemented on every day of the year so far.

While power curtailment interrupted production, AMSA attributed the 62% fall in headline earnings to R2.6-billion last year to weaker prices in the second half of the financial year and softer domestic demand.

Nevertheless the revenue and cost impact of power disruptions during the year was estimated to be about R275-million.

Earnings before interest, taxes, depreciation and amortisation slumped by 50% to R4.3-billion, as the “negative price-cost effect impacted margins”.

The group stressed that a reliable electricity supply was vital to the sustainability of the steel value chain, and reported that several Eskom and municipal equipment failures had been experienced in the second half of 2022.

“The company has made progress on operational planning and scheduling to better accommodate electricity disruptions.

“However, load curtailment may still interrupt production of rolling and finishing mills, which, in turn, can affect production and delivery to customers, especially of high-demand products,” AMSA warned.

Besides investing in its own electricity supply, AMSA is also studying the viability of pursuing a third-party rail solution, given that its operations are continuing to be negatively affected by the collapsing performance of Transnet Freight Rail (TFR).

Ongoing rail disruptions were a feature of “the entire financial year” and led to plant closures and affected sales deliveries, which had a net negative impact on earnings of about R1.3-billion.

“Daily briefings to the CEOs of ArcelorMittal South Africa and TFR have been beneficial, but overall performance remains well below service design.

“At the same time as offering support to TFR and Transnet Port Terminals, the company has completed the prefeasibility study with its specialist rail operator adviser into the commercial viability of third-party rail access.

“It has been agreed to progress to the definitive feasibility study stage, which includes funding solutions,” Verster reported.

TFR’s initial efforts to sell slots to third-party operators for a limited two-year duration were not highly successful, but recent developments indicated that the State-owned enterprise was open to pursuing longer-term partnerships.

In January, Transnet announced that it would issue a request for qualifications for the operation and maintenance of the Container Corridor between Johannesburg and Durban for a period of 20 years.

The move could open the way for third-party access on other corridors too, including those servicing AMSA.

Verster said the group was mainly keen to secure a better rail service and lower tariffs on the corridor that transports iron-ore from the Northern Cape to Vanderbijlpark, but he indicated that the Newcastle operation would receive the biggest immediate benefit from a third-party solution.

Edited by Creamer Media Reporter

Comments

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024
Resources Watch
Resources Watch
17th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.139 0.181s - 92pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: