Araguaia ferronickel project, Brazil – update

Ferronickel shots produced from the Araguaia pilot plant

Photo by Horizonte Minerals

22nd July 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Araguaia ferronickel project.

Location
Pará state, Brazil.

Project Owner/s
Horizonte Minerals.

Project Description
A feasibility study has confirmed Araguaia as a Tier 1 project with a large, high-grade scalable resource, long mine life and low-cost source of ferronickel for the stainless steel industry.

The project has two principal mining centres – Araguaia nickel south (ANS) and Araguaia nickel north (ANN). ANS hosts the Pequizeiro, Baiao, Pequizeiro West, Jacutinga, Vila Oito East, Vila Oito West and Vila Oito deposits, while ANN hosts the Vale do Sonhos deposit.

The feasibility study envisages an openpit nickel laterite mining operation that delivers ore from several pits to a central rotary kiln electric furnace (RKEF) metallurgical processing facility.

The deposits will be mined by contractors using conventional openpit truck-and-shovel techniques. No blasting will be necessary. Reverse circulation grade-control drilling will be completed at a 10 m × 10 m spacing, well ahead of mining. This, combined with visual control of the limonite and transition boundary, face sampling, stockpile sampling and ore feed sampling, supports a comprehensive mine-to-mill strategy that is designed to maintain consistent feed to the process plant.

Waste will be stored in external dumps near the pits. Ore will be transported to stockpile hubs near each deposit. Sheeting (using ferricrete extracted from the overburden) will be required to support trafficability in and around the mine during the wet season. Depending on plant demand, ore will be hauled from hub stockpiles or directly from the pits to the run-of-mine (RoM) at the RKEF process facility. Stockpiles on the RoM will be sheeted and classified according to ore type and chemistry for blending.

After an initial ramp-up period, the plant will reach full capacity of about 900 000 t/y of dry ore feed to produce 52 000 t/y of ferronickel containing 14 500 t/y of nickel.

The project has an initial 28-year mine life.

Araguaia’s feasibility study design allows for the future construction of a second RKEF process line, with potential to double Araguaia’s production capacity from 14 500 t/y to 29 000 t/y of nickel.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The base case estimates a post-tax net present value, at an 8% discount rate, of $401-million and internal rate of return of 20.1%.

Capital Expenditure
The project has a capital cost of $443-million, including $65.3-million in contingencies.

Planned Start/End Date
The RKEF plant and project infrastructure will be built over a 31-month period.

The company aims to start production in early 2021.

Latest Developments
Horizonte Minerals has awarded all major and long-lead-time process plant equipment contracts for the Araguaia project.

Horizonte will work with FLSmidth, Metso Outotec, Uvån Hagfors Teknologi Inteco Melting and Casting Technologies, as well as other leading suppliers to the ferronickel industry.  

The first pieces of equipment are expected on site during the fourth quarter of this year, in line with the overall project schedule.

To date, Horizonte has awarded contracts totalling $293-million on budget and on time. 

Key Contracts, Suppliers and Consultants
Ausenco Engineering Canada (process plant design); FLSmidth, Metso Outotec, Uvån Hagfors Teknologi Inteco Melting and Casting Technologies (equipment supply and technical support); and Hatch (furnace contract).

Contact Details for Project Information
Horizonte Minerals, tel +44 203 356 2901.
Tavistock, on behalf of Horizonte Minerals, tel +44 207 920 3150 or email horizonte@tavistock.co.uk.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Mining Weekly Editor Martin Creamer
Copper shares soar and green hydrogen goes digital
26th April 2024
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.137 0.202s - 93pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: