AngloGold gets enviro permits for Obuasi mine redevelopment

6th July 2018

By: Marleny Arnoldi

Online News Editor

     

Font size: - +

Gold miner AngloGold Ashanti has received environmental permits for its Obuasi gold mine, in Ghana, paving the way for the redevelopment of the large, high-grade orebody.

The granting of the permits by Ghana’s Environmental Protection Agency follows Parliamentary ratifications of the regulatory and fiscal agreements that cover the redevelopment of the Obuasi mine, including a development agreement, a tax concession agreement, a security agreement and a reclamation security agreement.

AngloGold CEO Srinivasan Venkatakrishnan said last week the redevelopment of the Obuasi mine as a modern and productive operation would progress and benefit stakeholders for at least two decades.

The mine had been in a limited operating phase since 2014, owing to the mine operating at significant losses for a prolonged period.

A previously published feasibility study on Obuasi found a 5.8-million-ounce ore reserve and 34-million-ounce mineral resource. Mine production for the first ten years will be focused on the upper orebodies and is expected to average 350 000 oz to 45 000 oz at an average head grade of 8.1 g/t gold.

The redevelopment will establish Obuasi as a mechanised underground mining operation.

The project implementation will be undertaken in two phases. Phase 1 comprises project establishment, mine rehabilitation and development, as well as plant and infrastructure refurbishment, to enable production at a rate of 2 000 t/d for the first year of operation.

Phase 1 is expected to take about 18 months, with the first gold pour expected in the third quarter of 2019.

The second phase includes refurbishment of the underground materials handling system, shafts and ventilation, and construction of the primary crusher, the semiautogenous grinding mill circuit, carbon regeneration, a new gold room and a tailings storage facility.

The second phase is expected to take a further 12 months and will enable production to increase to 4 000 t/d. The operation is then expected to ramp up to 5 000 t/d over the following three years.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Lilak Aluminium
Lilak Aluminium

For over 15 years, Lilak Aluminium, a trusted leader in architectural extrusion supply, has delivered excellence to businesses like yours.

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.054 0.741s - 110pq - 2rq
Subscribe Now