Name of the Project
Ana Paula gold/silver project.

Location
The Ana Paula project is located in the Guerrero gold belt, in the state of Guerrero, Mexico.

Client
Timmins Gold.

Project Description
The project proposes to develop a greenfield openpit gold/silver mine and a gravity/flotation/carbon-in-leach process plant, with a production rate estimated at 6 000 t/d.

Average production has been estimated at 116 000 gold ounces a year and 239 000 silver ounces a year over an 8.2-year mine life.

A total of 17.8-million tonnes of mineralised resource can be mined and processed, with 33.6-million tons of waste and 12.5-million tonnes of capitalised waste. Some of the capitalised waste rock will be stockpiled and an undetermined portion may be reclassified as a resource at a later date, should metallurgical testwork support economic viability.

The flowsheet selected for Ana Paula consists of a primary crushing, grinding (semiautogenous mill, ball mill and vertical mill), gravity recovery, flotation, disposal of flotation tails, leaching of a combined gravity and flotation concentrate, and recovery of precious metals using carbon-in-leach.

Jobs to be Created
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 5% discount rate, of $408-million, and an internal rate of return of 59%, with a payback of 1.6 years.

Value
Initial capital costs are estimated at $121.7-million, including contingency costs of $19.8-million.

Duration
Not stated.

Latest Developments
Timmins has approved a preconstruction programme, including the start of a $9.2-million feasibility study, for the Ana Paula project. Preconstruction activities will start immediately and will include feasibility work, infill drilling and metallurgical testwork, as well as environmental baseline and permitting activities. The company expects the feasibility study to be completed by the third quarter of 2017 and to have all the permits required to start construction by the first quarter of 2018.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Timmins Gold, tel +1 604 682 4002, fax +1 604 682 4003 or email info@timminsgold.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Lilak Aluminium
Lilak Aluminium

For over 15 years, Lilak Aluminium, a trusted leader in architectural extrusion supply, has delivered excellence to businesses like yours.

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.044 0.707s - 111pq - 2rq
Subscribe Now