https://www.miningweekly.com

Alexander coal project, South Africa

17th April 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Alexander coal project.

Location
The project will be located in Mpumalanga, South Africa.

Project Owner/s
Sasol Mining.

Project Description
The proposed project forms part of Sasol Mining’s plan to fulfil its 2050 mandate of supplying coal to Secunda Synfuels operations.

The aim of the project is to deploy production sections within the Alexander coal blocks. There are three coal blocks that will be
mined.

The project is expected to yield between six- and eight-million tonnes of coal a year.

Potential Job Creation
Not stated.

All-in Sustaining Costs/All-in Costs
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
Not stated.

Latest Developments
Gibb Mining has been awarded the tender to complete a feasibility study for Sasol Mining’s Alexander project.

Jones and Wagener will conduct the environmental portion of the feasibility study, while Gibb Mining will be responsible for all geotechnical and geohydrological aspects, with Jones and Wagener acting as subconsultants to Gibb Mining in this regard.

Gibb Mining will also be responsible for the mine design and associated planning, specifically access to the coal reserve through a boxcut and its tie-in to Sasol Mining’s overall long-term complex plan.

In addition to the mine design, Gibb Mining will also be responsible for the materials handling system design and all supporting infrastructure, which includes offices, buildings, workshops, a 20 km mine access road and the supply of bulk water and bulk power to the mine.

Gibb Mining is working on the feasibility engineering designs. Once these are finalised and accepted by Sasol Mining, the company will compile a capital cost estimate based on the design, all of which will be incorporated into a feasibility study report for issue to Sasol Mining by the end of July.

Gibb Mining’s designs will need to consider all environmental constraints, as well as incorporate new technological developments that will bring efficiencies to the project and the mine operation, in terms of cost, safety and water and energy efficiency.

Key Contracts and Suppliers
Gibb Mining (feasibility study) and Jones and Wagener (environmental studies).

Contact Details for Project Information
Sasol head of group media relations Alex Anderson, tel +27 10 344 6509 or email alex.anderson@sasol.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.046 0.826s - 111pq - 2rq
Subscribe Now