Alcyone close to offtake deal
PERTH (miningweekly.com) – Silver miner Alcyone Resources has restarted silver recoveries at its Texas project, in Queensland, with the miner telling shareholders that it was on the verge of securing a silver purchase agreement.
Alcyone noted on Monday that following the restart of the crushing operation several weeks ago, silver recovery operations restarted over the weekend, with the first shipment of dore bars expected prior to the end of the month.
The company has revamped the crushing plant at the Texas mine, bringing the plant’s capacity to 1.1-million ounces a year. The final work of the upgrade would occur during an operational shutdown in the last two weeks of September.
Alcyone noted that once the upgrade was complete, the circuit would deliver some 85 000 t of ore to the heap leach each month, providing the basis for a significant increase in production levels during early 2014.
Meanwhile, the silver miner said on Monday that it was currently in discussions with a number of precious metal streaming funds regarding a silver purchase agreement.
It was anticipated that the agreement would deliver an upfront payment of up to $10-million in exchange for the right to purchase up to 15% of Alcyone’s silver production from the Texas project at a low fixed cost, over the life of the mine.
The purchase agreement would also accelerate production growth, with significant development and operational expansion forecast upon completion.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation