Agbaja iron-ore project, Nigeria
Name and Location
Agbaja iron-ore project, Kogi state, Nigeria.
Client
Kogi Iron.
Project Description
Kogi Iron is targeting a five-million-tonne-a-year iron-ore operation at Agbaja.
As part of the mine planning and scheduling study for the project, the company has identified a possible location for a processing plant and has completed the design of pit shells within two stage areas identified for mining operations.
The proposed plant site location is in the north-east of the resource area and has been selected based on its central location between the two areas (Stage 1 and Stage 2) identified for mining operations.
The Stage 1 mining area, situated to the west of the proposed plant site, comprises about 6 km2 and is west of the proposed plant site. This area contains about 158-million tonnes of the 488-million-tonne inferred mineral resource.
Targeting the magnetic fraction of the mineral resource, the average grade of material identified for mining is estimated at about 46% iron, with a corresponding strip ratio of about 0.68:1. This area should provide processing plant feed for an initial 14 years.
The Stage 2 mining area of about 2.2 km2 is situated to the east of the proposed plant site. This area is estimated to contain 63-million tonnes of the 488-million-tonne inferred mineral resource. The average grade of material identified for mining is estimated at 46% iron, with a corresponding strip ratio of approximately 0.81:1. This area should provide processing plant feed for an additional six years, bringing the combined total plant feed from the two areas to 20 years.
Value
Still to be confirmed.
Duration
Still to be confirmed.
Latest Developments
The next phase in the project is the estimation of mining costs using quotations that are being submitted by several leading mining contractors in response to requests for proposals.
The scoping study is on track for completion by the end of the first quarter of 2014.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Kogi Iron, tel +61 8 9200 3456 or email info@kogiiron.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation