https://www.miningweekly.com

Eskom says ‘unexpected challenges’ during Koeberg Unit 1 outage will delay restart

7th April 2023

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

The first Unit 1 steam generator at the Koebergpower station has been removed from the containment building and placed into an on-site storage building – a development that Eskom describes as a major milestone for a project that has had numerous false starts during previous outages.

However, the State-owned utility has also confirmed that, as a result of “unexpected challenges” during the current long-duration outage, the original return to service date of early June is “no longer achievable”.

“Although every effort is being made to reduce the impact, we are currently running a few weeks late,” Eskom said in a statement, adding that the generation production plan was being updated to minimise the impact of the projected delay.

However, Electricity Minister Kgosientsho Ramokgopa later revealed that the project was running 45 days behind schedule, which meant the unit was now unlikely to be available to support South Africa through the high-demand winter period. The removal of the first steam generator came only days after the National Nuclear Regulator (NNR) announced that the 60-day period for receiving written representations from members of the public on Koeberg’s application to operate beyond its mid-2024 licence expiry date had closed.

While central to the utility’s plan to extend the life of the nuclear power station for a further 20 years, the replacement project has faced heavy criticism from both environmental groups and energy commentators.

Environmental opponents to the extension have already raised concerns about the consultation process being pursued by the NNR and have also expressed anxiety about the safety case for the life extension, as well as with the project’s rising costs and corruption at Eskom.

Questions are also continually being raised about the direct and indirect costs of the project, with Eskom having acknowledged that the 2010 cost estimate of R20-billion is no longer accurate but has not yet provided a revised expenditure figure.

The indirect costs, meanwhile, have also been calculated to be substantial, given ongoing loadshedding and the fact that having a Koeberg unit out of service for most of 2023 will add one stage to loadshedding when such cuts are implemented.

Once the Unit 1 replacement is completed, Eskom intends pursuing a similar long-duration outage at Unit 2, leaving Eskom without electricity production from half of Koeberg for most of 2023.

The Unit 1 outage began on December 10 and was expected to continue for about 180 days, while Unit 2 will be shut in September for a similar period after a previous attempt to replace the steam generators was postponed when it emerged that Eskom’s storage facilities had not been completed in time.

Eskom insists, however, that the new steam generators are the last large component replacements needed to ensure Koeberg can operate safely for the requested additional 20-year period.

It also underlines the engineering and logistical complexity of the removal of the first steam generators, explaining that it involved moving steam generators that are installed vertically and taking them out of the containment building horizontally at an elevation of 20 m before placing them on a flatbed transporter.

The old steam generators are painted in a white coating as a preventative measure to eliminate the chance of spreading any surface contamination, before being placed in the storage facility that will be sealed with a concrete door. Eskom then has ten years to dispose of the steam generators.

In a statement, Eskom noted that each steam generator is 22 m long, or the height of a six-storey building, and weighs over 320 t, which the utility notes as being heavier than a Boeing 747.

Eskom also indicates that the removal and replacement of Unit 1’s other two steam generators will involve the following sequence of activities:

  • igging the remaining two steam generators out from their positions inside the containment building;
  • igging the three new steam generators into their exact position inside the containment building;
  • performing six critical welds (two on each steam generator) that join the steam generators to the primary system piping;
  • performing radiography on the welds to ensure they meet the code requirements;
  • peinstalling all the access platforms that enable people to work all the way up the steam generators (seven storeys of permanent structures and temporary scaffolding);
  • einstalling all the other piping connections (steam pipe at the top, feedwater pipe, and all the other smaller sampling and instrumentation connections) once access is available;
  • nstalling new thermal insulation over the whole steam generator surface and all the pipes that were worked on, with about 120 t having been removed; and
  • removing all the temporary equipment that was required to be installed to allow the work to be completed safely.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION