https://www.miningweekly.com
Construction|Crushing|Engineering|Excavator|Financial|Flow|Gas|Gold|Mining|PROJECT|Resources|Services|Storage|Flow|Environmental|Infrastructure
Construction|Crushing|Engineering|Excavator|Financial|Flow|Gas|Gold|Mining|PROJECT|Resources|Services|Storage|Flow|Environmental|Infrastructure
construction|crushing|engineering|excavator|financial|flow-company|gas|gold|mining|project|resources|services|storage|flow-industry-term|environmental|infrastructure

Warrawoona gold project, Australia – update

LOcation map of the Warrawoona project

Photo by Calidus Resources

8th July 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Warrawoona gold project.

Location
Pilbara, Western Australia.

Project Owner/s
Calidus Resources.

Project Description
The Warrawoona project is a high-margin gold operation, with average gold production estimated at 90 000 oz/y over an initial eight-year mine life.

The project has a global resource of 43.7-million tonnes grading 1.06 g/t gold for 1.5-million ounces.

The project includes a two-million-tonne-a-year conventional carbon-in-leach processing circuit with a single-stage crushing and semiautogenous grinding mill.

Calidus’ acquisition of the high-grade Blue Spec mine provides immediate opportunity to expand production and free cash flow at the project. The definitive feasibility study and integration plan are being undertaken in parallel with the construction of Warrawoona.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of A$408-million and an internal rate of return of 81%, with a payback of 13 months.

Capital Expenditure
The project has a capital cost of $120-million, including contingency and preproduction mining costs.

Planned Start/End Date
The project is expected to pour first gold in the first half of 2022.

Latest Developments
Calidus Resources poured 8 916 oz of gold in the June quarter during the commissioning and ramp-up of the Warrawoona gold project, with an additional 1 192 oz of gold in circuit.

First gold was poured in May, following the completion of the processing plant commissioning.

The gold produced to date has reconciled the resource and grade control models and resulted in the first debt repayment of A$3-million made to financial services provider Macquarie Bank as scheduled.

Milling rates also progressed throughout the June quarter and were expected to reach the nameplate capacity of 2.4-million tonnes a year in July.

Calidus reported a total of 327 000 t of low-grade ore, commissioning ore and run-of-mine ore milled during the quarter.

The process plant has been tested at up to 2.8-million tonnes a year, with no major bottlenecks identified, Calidus has said.

Mining has rapidly progressed, with 20 000 bank cubic metres (BCM) a day movement achieved, against an average requirement of 18 500 BCM/d. A new excavator and additional manning are to be mobilised in July to ensure that the BCM movement is maintained.

Liquefied natural gas storage vessels have been delivered to site, with a transition to gas-fired electricity expected in July.

Key Contracts, Suppliers and Consultants
Optiro Consultants, Lynn Widenbar and Associates (mineral resource estimate); Rapallo, Biologic, Woodman, Sticks and Stones, Total Heritage, Nyamal Heritage, Bat Call, Graeme Campbell and Associates, Mine Earth, Lloyd George Acoustics (environmental base line studies and project permitting); Peter O’Bryan and Associates, ATC Williams (geotechnical); ATC Williams (tailings storage facility); Groundwater Resource Management, or GRES (hydrology and hydrogeology); GR Engineering Services (processing plant); GRES, Metallurgy Management Services, Nagrom, ALS, BV (metallurgy and testwork); GRES, Aerodrome Management Services (infrastructure); Intermine Engineering Consultants, Entech and Galt Mining (mining); Macmahon Holdings (openpit mining and tailings dam); GRES (process plant engineering, procurement and construction contract); Rangecon (village install); and Telstra (communication).

Contact Details for Project Information
Calidus Resources, email info@calidus.com.au.

Edited by Creamer Media Reporter

Comments

Showroom

Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 
Aqs image
AQS Liquid Transfer

AxFlow AQS Liquid Transfer (Pty) Ltd is an Importer and Distributor of Pumps in Southern Africa

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 03 May 2024
Magazine round up | 03 May 2024
3rd May 2024
Resources Watch
Resources Watch
2nd May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.114 0.169s - 94pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: