https://www.miningweekly.com

Platreef palladium/platinum/rhodium/nickel/copper/gold project, South Africa – update

26th February 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Platreef palladium/platinum/rhodium/nickel/copper/gold project.

Location
Northern limb of South Africa's Bushveld Igneous Complex, in Limpopo.

Project Owner/s
Ivanhoe Mines indirectly owns 64% of the Platreef project through its subsidiary, Ivanplats, and is directing all mine development work.

The South African beneficiaries of the approved broad-based, black economic-empowerment structure have a 26% stake in the Platreef project. The remaining 10% is owned by a Japanese consortium comprising Itochu Corporation; Japan Oil, Gas and Metals National Corporation; Itochu affiliate ITC Platinum Development; and Japan Gas Corporation.

Project Description
Ivanhoe Mines has reported outstanding positive findings of an independent Platreef integrated development plan 2020 (Platreef IDP20) for the tier-one project. The project has total probable reserves estimated at 124.7-million tonnes as at November 30, 2020, for seven-million ounces of platinum, eight-million ounces of palladium, 1.2-million ounces of gold, 500 000 oz of rhodium, 457-million pounds of copper and 932-million pounds of nickel.

The Platreef IDP2020 encompasses two devel­opment scenarios. 

The Platreef 2020 feasibility study – an update of the 2017 feasibility study –  evaluates the development of a 4.4-million-tonne-a-year under­ground mine, with two concentrators built in modules of 2.2-million tonnes a year. This updates the 2017 feasibility study by taking into account the development achieved since 2017, as well as updated costs, metal prices and foreign exchange assumptions, in addition to increased throughput from four-million tonnes a year to 4.4-million tonnes a year to use the full processing capacity of the two concentrators.

The feasibility study has an average production of 508 000 oz/y of platinum, palladium, rhodium and gold, plus 22-million pounds of nickel and 13-million pounds of copper.

The alternative Platreef 2020 preliminary eco­nomic assessment (PEA), or phased development plan, evaluates the phased development of an initial 700 000 t/y underground mine using the existing Shaft 1 and a new 770 000 t/y concentrator, targeting high-grade mining areas with significantly lower capital costs. After first production is achieved, Shaft 2 sinking will start to coincide with the construction of two additional 2.2-million-tonne-a-year concentrator modules and the ramp-up of the initial concentrator to its full capacity of 770 000 t/y, increasing steady production to 5.2-million tonnes a year. Shaft 2 development may be brought forward to accelerate this expansion. The PEA envisages Phase 1 during years 1 to 6 at an average production 109 000 oz/y of plat­inum, palladium, rhodium and gold (3 PGE + Au), plus five-million pounds of nickel and three-million pounds of copper. Phase 2 – years 7 to 30 – average production is 613 000 oz/y of 3 PGE + Au, plus 27-million pounds of nickel and 16-million pounds of copper.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The feasibility study yields an after-tax net present value (NPV), at an 8% discount rate, of $1.85-billion and an internal rate of return (IRR) of 19.8% at a long-term consensus metal price, with a payback of 4.4 years. At spot metal prices, the feasibility study estimates an after-tax NPV, at an 8% discount rate, of $3.74-billion and IRR of 28.4%, with a payback of 3.2 years.

The PEA yields an after-tax NPV, at an 8% discount rate, of $1.61-billion and IRR of 20% at long-term consensus metal prices, and an after-tax NPV, at an 8% discount rate, of $3.3-billion and IRR of 29.1% at spot metal prices. Payback at long-term consensus metal prices is estimated at 8.4 years and at spot metals prices at 7.3 years.

Capital Expenditure
The Platreef 2020 feasibility study estimates initial capital costs for the project at $1.4-billion.

The PEA estimates an initial capital cost of $390-million. Expansion capital is estimated at $1.27-billion.

Planned Start/End Date
The Platreef IDP20 envisages Shaft 2 equipped for hoisting in 2025, allowing for first concentrate production in the latter half of the year. The PEA envisages first concentrate production for this option in 2024, with the sinking of Shaft 2 restarting in 2025 to coincide with the con­struction of two 2.2-million-tonne-a-year concentrators to be completed by 2029 and 2030.

Latest Developments
Ivanplats is arranging project-level financing of up to $420-million for the development of its Platreef project.

It has signed a nonbinding termsheet with Orion Mine Finance for a $300-million streaming facility and has appointed Societe Generale and Nedbank as mandated lead arrangers for a senior project debt facility of up to $120-million.

“We are confident that this project-level funding will be the catalyst needed to launch Platreef to become a leading, long-life supplier of palladium, platinum, rhodium, nickel, copper and gold,” Ivanhoe co-chairperson Robert Friedland has said.

“The production of key ‘green metals’ needed to reduce greenhouse-gas emissions is at a critical inflection point, as businesses are pressed to secure long-term supplies.’

Meanwhile, Ivanhoe reports that detailed engineering is under way on the mine design, 770 000 t/y concentrator and associated infrastructure for the phased development plan, which is scheduled to be incorporated into an updated feasibility study before the end of 2021.

Platreef’s budget for 2021 is $59-million, which includes $10-million to start the construction of the headframe for Shaft 2. The first draw from the streaming funds, which is expected to occur shortly after establishment of the facility, is expected to fully cover Platreef’s 2021 budget.

The senior project debt facility will be used only after the streaming facility is fully drawn down.

Key Contracts, Suppliers and Consultants
OreWin (Platreef IDP20).

Contact Details for Project Information
Ivanhoe Mines, tel +27 11 088 4300 or email info@ivanhoemines.com.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION