https://www.miningweekly.com

Haib copper project, Namibia – update

20th October 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Haib copper project.

Location
Partially in the Namaqua-Natal province, in Namibia, called the Richtersveld geological subprovince.

Project Owner/s
Mineral explorer and developer Deep-South Resources, through its subsidiary Haib Minerals.

Project Description
An updated preliminary economic assessment (PEA) has shown the Haib project to be amenable to bioheap-leaching.

The PEA envisages a life-of-mine of 24 years and a throughput of 20-million tonnes a year, with copper recovery estimated at 80%, and production estimated at 35 332 t/y of copper cathode and 51 081 t/y of copper sulphate.

The mine design is based on openpit methods. As the deposit comprises hard-rock material, the mining operations will involve the drill and blast of all excavated material, which will be segregated by cutoff grade.

The mining fleet will consist of appropriately sized hydraulic excavators and off-highway dump trucks, supported by standard opencut drilling and auxiliary equipment.

There will not be any tailings. The spent heaps will be rehabilitated and left in place. Owing to environmental reasons and water resources, the tailings from the pH adjustment process and the iron removal process will be disposed onto the spent heaps using filtered dry-stacked tailings.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a discount 7.5% rate, of $977-million, and an internal rate of return 30.1%, with a payback of 4.22 years.

Capital Expenditure
Capital expenditure is estimated at $341-million.

Planned Start/End Date
Not stated.

Latest Developments
Deep-South Resources has entered into an agreement with Namibian drilling contractor Ferrodrill Namibia to proceed with the drilling programme.

The contract provides for 5 000 m of diamond drilling. The specific focus is to drill the high-grade area of the deposit uncovered by Deep-South in 2019. It is planned that up to 10 000 m in the area will be drilled. The first 5 000 m were drilled in 2021.

Deep-South's goal is to complete the remaining 5 000 m of drilling and then proceed with a new resource estimation.

It has appointed South Africa-based consultancy Knight Piésold Consulting to conduct an environmental- and social-impact assessment (ESIA) on the Haib project.

The ESIA will accompany a feasibility study for the eventual filing for a mining licence.

The ESIA will comprise environmental, social and hydrogeological feasibility studies, as well as a public participation programme required for assessing the overall feasibility of the proposed project and obtaining the necessary authorisations.

Key Contracts, Suppliers and Consultants
METS Engineering Group (updated PEA); Knight Piésold Consulting (scoping studies and assessments); Csiro (conduct bio-assisted heap-leaching column testwork); METS Engineering Group of Australia (testwork supervision); MSA Group (NI 43-101-compliant mineral resource estimate); Knight Piésold Consulting (ESIA) and Ferrodrill Namibia (drilling contract).

Contact Details for Project Information
Deep-South Resources (Namibia), tel +264 61 435 8267 or email info@deepsouthresources.com.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION