Eskom ‘sets the record straight’ on its dealings with Glencore

7th November 2016

By: African News Agency

  

Font size: - +

JOHANNESBURG – Recent media reports quoting Glencore as vehemently denying it had ever proposed coal price increases of more than R300/t to Eskom “cannot go unchallenged”, the electricity parastatal said on Sunday.

“It is unfortunate that Glencore has suggested that Eskom has lied about Optimum Coal Mine wanting to increase the coal prices to R570/t,” it said in a statement to “set the record straight”.

Following failed attempts by Optimum to renegotiate and extend the coal supply agreement for the Hendrina Power Station at prices higher than the R150/t contractual agreement, Optimum later proposed a “compromise deal”. In terms of the proposed deal, the coal supply agreement to the Hendrina Power Station would be renegotiated at R300/t until 2018, and thereafter be extended to 2023 at R570/t, the statement said.

In a letter dated 30 June 2015, Optimum said: “The base price for the first period and second period shall be escalated on each anniversary of the base date in accordance with a price adjustment factor which is to be calculated in accordance with an escalation table to be agreed between Eskom and Optimum.”

“In another letter dated 17 September 2015, when Optimum was under business rescue, they proposed a price increase of R630/t and a coal supply agreement extension until 2023.

“In that letter, the business rescue practitioners proposed a coal price increase of R443/t with effect from 1 October 2015 to 31 December 2018. Thereafter the price would increase to R630/t until 2023.”

Eskom said it was not involved in the sale agreement between Glencore and Tegeta. “All Eskom was interested in was to ensure that the new owners were aware that the coal prices, volumes, and quality would not be renegotiated or compromised, and that the penalties imposed on Optimum would not be waivered. Nothing has changed since then even though Optimum Coal Mine is under new management,” the statement said.

Edited by African News Agency

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION